Pipes & Wires

THE JOURNAL OF ENERGY & INFRASTRUCTURE THOUGHT LEADERSHIP

Issue 82 – May 2009

 

From the director…

 

Welcome to Pipes & Wires #82. This month starts with some extensive analysis of several regulatory decisions from Australia. We then dive into a wide array of policy examination, with examination of competition policy in the UK and Europe and then energy policy in the US, France and the UK. Issue #82 then closes with an examination of the judicial review of a major transmission investment decision in new Zealand.

 

About Utility Consultants

 

Utility Consultants Ltd is a management consultancy specialising in the following aspects of energy and infrastructure networks…

 

·      Mergers & acquisitions

 

·        Asset management

·      Strategic studies

 

·        Financial analysis

·      Economic & structural regulation

·        Risk management

 

To be sent a detailed profile of recent projects, pick this link.

 

Regulatory determinations

 

Aus – varying GasNet’s access arrangement

 

Introduction

 

Most of us appreciate that any tariff determination is based on projections and assumptions that look forward 5 years, and would understand that any robust regulatory regime will include provision to review the determination if there are material changes to the underlying costs, asset configurations or operating modes. Following on from discussions in Pipes & Wires #66 and #73, this article examines GasNet’s 2nd requested variation and the AER’s draft response.

 

Background

 

The prevailing regulatory framework is the National Gas Rules (NGR), and in particular Rule 65 which provides for a pipeline owner to seek a variation to an access arrangement.

 

GasNet’s variation proposal

 

The basis of GasNet’s proposed variation is the changes in the way compressor fuel gas is treated under the Victorian gas industry Market & System Operation Rules which effects the application of tariffs for the Western Underground Gas Storage (WUGS) and the SEA Gas connection points. GasNet proposed a number of variations including removing the WUGS Transmission Refill Tariff and applying the standard South West Zone withdrawal tariff to all withdrawals from WUGS (understanding why GasNet sought the variation requires an understanding of the asset configuration and operating modes, which are described in the AER’s draft decision).

 

The AER’s draft decision

 

In its draft decision of April 2009, the AER proposes to decline GasNet’s proposed variation for several reasons. The AER notes that while GasNet has raised some valid issues, the AER is concerned about GasNet’s proposed means of addressing those issues.

 

Aus – final electricity distribution determinations

 

Introduction

 

In April 2009 the Australian Energy Regulator (AER) released its Final Decisions for the electricity distributors in New South Wales and the Australian Capital Territory. This article examines those decisions in the context of the Draft Decisions of December 2008 that were examined Pipes & Wires #78.

 

Background

 

The legal framework for electricity price decisions is the National Electricity Rules (NER), which includes the following requirements…

 

·         The requirement for an electricity distributor to submit a Proposal for the next price control period 13 months prior to the start of that period. The next control period for the NSW-ACT distributors (Integral Energy, EnergyAustralia, Country Energy and ActewAGL) starts on 1 July 2009, hence their Proposals had to be submitted by 31st May 2008.

 

·         Setting out what a Proposal must contain.

 

·         The requirement for the AER to make its Final Decision at least 2 months prior to the start of the next control period.

 

Comparison of Proposals and Draft Decisions

 

The following table compares the Proposals, the Draft Decisions and the Final Decisions…

 

Parameter

Integral Energy

EnergyAustralia

Country Energy

ActewAGL

Prop.

Draft

Final

Prop.

Draft

Final

Prop.

Draft

Final

Prop.

Draft

Final

Opening RAB ($m)

$3,835m

$3,678m

$3,690m

$8,218m

$8,188m

$8,325m

$4,236m

$4,247m

$4,319m

$593m

$588m

$598m

CapEx ($m)

$2,953m

$2,914m

$2,721m

$8,659m

$8,435m

$7,838m

$4,008m

$3,955m

$3,826m

$287m

$278m

$275m

OpEx ($m)

$1,477m

$1,460m

$1,516m

$3,047m

$2,638m

$2,628m

$2,160m

$1,975m

$2,052m

$359m

$296m

$341m

Depreciation ($m)

$482m

$568m

$608m

$609m

$600m

$626m

$716m

$784m

$814m

$87m

$89m

$94m

Revenue ($m)

$4,695m

$4,632m

$4,485m

$10,009m

$9,447m

$8,786m

$5,978m

$5,819m

$5,672m

$823m

$779m

$793m

WACC

9.76%

9.72%

8.83%

9.76%

9.72%

8.78%

9.76%

9.72%

8.78%

10.7%

9.82%

8.79%

 

Pipes & Wires will continue its examination of the Australian distribution Decisions towards the end of 2009 when the Draft Decisions for SA and Queensland emerge.

 

Aus – final electricity transmission determinations

 

Introduction

 

Pipes & Wires #73 noted the Regulatory Proposals submitted by two Australian electricity transmission businesses, TransGrid in NSW and Transend in Tasmania. This article examines the Australian Energy Regulators’ (AER) Draft and Final Decisions (and my apologies that an article examining the Draft Decisions never happened).

 

Comparing the Proposal, Draft and Final Decisions

 

The key features of each Proposal, Draft and Final Decision included…

 

Parameter

TransGrid

Transend

Prop.

Draft

Final

Prop.

Draft

Final

Total CapEx

$2,627m

$2,377m

$2,405m

$681m

$615m

$606m

Total OpEx

$855m

$765m

$758m

$281m

$260m

$254m

Nominal risk free rate

5.70%

5.46%

4.29%

6.37%

5.27%

4.30%

Nominal vanilla WACC

9.15%

9.82%

8.79%

10.65%

9.64%

8.80%

Opening asset base

$4,237m

$4,234

$4,218m

$987m

$994m

$951m

Smoothed P0

0%

0%

0%

-28.5%

-18.9%

0%

Smoothed X

-5.59%

-4.39%

-4.10%

-6.4%

-5.8%

-5.2%

 

Pipes & Wires will continue its examination of the Australian decisions towards the end of 2009 when the Draft Decisions for the SA and Queensland distributors emerge.

 

Aus – final decision on WACC

 

Introduction

 

Pipes & Wires #75 and #79 examined the Australian Energy Regulator’s (AER) planned review of the WACC components that would apply to all forthcoming wires decisions. This article summaries the AER’s final decisions and compares them to the proposed conclusions that were set out several months ago.

 

Comparing the proposed and final conclusions

 

The AER’s proposed and final conclusions are compared below...

 

Proposed conclusions

Final conclusions for transmission and distribution

The nominal risk-free rate (Rf) shall be based on a moving average annualised yield on Commonwealth Government bonds having a maturity period that matches the term of the control period.

The nominal risk-free rate (Rf) shall be based on a moving average annualised yield on Commonwealth Government bonds. However the maturity period shall be 10 years.

The time period during which the risk-free rate is to be calculated shall be a period proposed by the TNSP or DNSP that is as close as practically possible to the start of the control period, or some other period specified by the AER if it does not agree with the period proposed.

The time period during which the risk-free rate is to be calculated shall be a period proposed by the TNSP or DNSP that is as close as practically possible to the start of the control period, or some other period specified by the AER if it does not agree with the period proposed.

The equity beta (βe) shall be reduced from the current range of between 0.9 and 1.0 to a lesser figure of 0.8.

The equity beta (βe) shall be 0.8.

The market risk premium (MRP) shall remain unchanged at 6.0%.

The market risk premium (MRP) shall be 6.5%.

The ratio of debt to (debt + equity) shall remain unchanged at 0.6.

The ratio of debt to (debt + equity) shall remain unchanged at 0.6.

The benchmark credit rating shall increase from BBB+ to A-.

The benchmark credit rating shall remain at BBB+.

The assumed utilisation of imputation credits (γ) shall increase from 0.5 to a greater figure of 0.65.

The assumed utilisation of imputation credits (γ) shall increase from 0.5 to a greater figure of 0.65.

 

Disclaimer

 

Readers should read all relevant AER publications in their entirety. Neither Utility Consultants Ltd nor its shareholder or directors shall be responsible for any action or failure to act based on this article.

 

Competition policy

 

Europe – concluding the gas market investigation

 

Introduction

 

Accusations of anti-competitive behavior in the energy sector are certainly not uncommon. This article examines the EU’s recent investigation into alleged anti-competitive behavior by German gas transmission utility RWE Transportnetz Gas.

 

Background to the investigation

 

In May 2006, the EU Competition Commission commenced an investigation into the German energy market as an adjunct to the energy sector competition inquiry (which was discussed in Pipes & Wires #56 and #58). Anti-trust proceedings were then opened against RWE a year later in May 2007.

 

The legal basis of anti-competitive behavior

 

The legal basis of anti-competitive behavior is based on Article 82 of the EC Treaty which prohibits a business that holds a dominant position in an EU market from abusing that position. Abusing a dominant position is defined to include inter alia

 

·       Directly or indirectly imposing unfair purchase or selling prices or other unfair trading conditions.

 

·       Limiting production, markets or technical development to the prejudice of consumers.

 

·       Applying dissimilar conditions to equivalent transactions with other trading parties, thereby placing them at a competitive disadvantage.

 

·       Making the conclusion of contracts subject to acceptance by the other parties of supplementary obligations which, by their nature or according to commercial usage, have no connection with the subject of such contracts.

 

Within this broad framework of competition law, the Commission needs to act in accordance with Chapter III of Regulation 1/2003 and Regulation 773/2004. The detail of this is beyond the scope of this article, but the important feature to note is that Article 9 of Regulation 1/2003 allows the Commission to turn a voluntary commitment by a business into a legally binding requirement.

 

The EU’s accusations

 

The EU Competition Commission believes that RWE’s behavior may have been anti-competitive on the following 2 counts…

 

·       RWE may have refused access to its network, ostensibly by using its dominant role to keep the network’s transmission capacity all to itself.

 

·       RWE may have intentionally set its transmission tariffs at an artificially high level to squeeze the margins of those competitors that did have access to the network.

 

The required remedy

 

In order to avoid a fine of up to 10% of its revenues (which would amount to about €1b), RWE has undertaken to sell its gas transmission network. The Commisson’s acceptance of RWE’s undertaking escalates that undertaking into a legally binding commitment pursuant to Article 9 of Regulation 1/2003, but in return closes the anti-trust investigation. RWE must sell the network to an entity that does not have an interest in allocating transmission capacity. The sale will be overseen by a Trustee with the final sale being approved by regulators.

 

For its part, RWE says its commitment to sell the network is not an admission of guilt, but simply represents a prudent business decision to avoid protracted litigation.

 

UK – selling the airports

 

Introduction

 

It’s been a long while since Pipes & Wire’s has discussed airports, but a recent decision in the UK that is in keeping with a common theme of competition law makes for some interesting analysis and comment. This article examines the Competition Commission’s conclusion that common ownership of airports within geographical clusters was restricting competition.

 

Background

 

The British Airports Authority owns 7 airports in the UK that fall into 2 broad geographical clusters – Heathrow, Gatwick, Stansted and Southampton in the south of England, and Glasgow, Edinburgh and Aberdeen in Scotland.

 

In March 2007 the Office of Fair Trading referred the supply of airfield services in these markets to the Competition Commission for investigation. The Office believed it had reasonable grounds for suspecting that a feature or combination of features in the market or markets in which BAA supplies airfield services prevents, restricts or distorts competition.

 

The Commission’s findings

 

In March 2009 the Commission released its findings, which were broadly as follows...

 

·       That BAA’s common ownership of airports in south-east England and lowland Scotland gives rise to adverse effects on competition in the markets for airfield services.

 

·       That Heathrow is the only significant hub in the south-east, or indeed in all of England.

 

·       That Aberdeen is geographically isolated and it would be unattractive to establish a competing airport.

 

The Commission’s recommended remedies included...

 

·       That Stansted and Gatwick be sold to different organisations.

 

·       That Edinburgh or Glasgow be sold.

 

BAA’s response to the Commission’s remedies

 

BAA’s official response was very measured. The need to change is recognised, and BAA clearly notes that is attempting to improve its service levels and had already commenced the sale of Gatwick in September 2008.

 

Perhaps more importantly in the context of Pipes & Wires’ on-going examination of competition law and its usual consequences, the climate for selling infrastructure businesses is not exactly good at the moment.

 

Energy policy

 

US – the super-grid question

 

Introduction

 

As the move away from fossil-fuelled generation intensifies (particularly towards wind) and electric utilities seek better utilisation of generation plant, interconnection of grids is a hot topic. This article examines the possibility of a super-grid that was discussed in a recent article by the Manhattan Institute.

 

Some engineering background to interconnection

 

For those who aren’t from an engineering background, the principle of interconnection exploits the different times at which individual customers’ demand peaks (and it only takes about 20 houses to get a reasonable diversity). This enables expensive peaking plant to be avoided, and as interconnection spreads it begins to further exploit factors such as time zones and weather zones (which now includes catching wind over as wider area as possible).

 

The value of interconnection

 

The article by the Manhattan Institute estimates that market price spreads and under-utilised capital add about 5c to 6c per kWh whilst a nation-wide super-grid could move about 25% of the nations’ generation at less than 0.5c per kWh. So whatever the precise numbers are, it probably does merit a further look.

 

The plans for a super-grid

 

Late last year Electric Transmission America (ETA) raised the profile of a possible 765kV super-grid, ostensibly using the environmental argument that less corridor width is required than for the equivalent power transfer at 345kV or 500kV.

 

ETA’s partners are American Electric Power (AEP) and MidAmerican Energy Holdings, so the background in 765kV transmission is certainly well established. ETA also sees itself as being well positioned to overlay a 765kV super-grid on the existing grids emphasising that this will facilitate wind generation and will enable markets that are currently exposed to fossil fuel price volatility to obtain lower and more certain prices.

 

Mixing grids and markets

 

The roll-out of a super-grid overlaying existing grids would, on the face of it, remove transmission constraints that are leading to price spreads between markets (the very thing that the Manhattan Institute article discussed). If we connect this to the current threat of unbundling in Europe (especially E.On’s planned voluntary sale of its UHV grid business E.On Netz) and the underlying reasoning that a grid owner can manipulate energy supply decisions to its own advantage, the super-grid could require a careful policy framework.

 

France – examining the nuclear policy

 

Introduction

 

Pipes & Wires #81 consolidated some previous ad-hoc examinations of nuclear policies in Sweden, Germany and the UK. This article continues that theme with a brief look at France’s nuclear policy.

 

France’s current dependence on nuclear power

 

France has the highest dependence on nuclear power in the world ... between 75% and 90% of France’s electricity is generated by 59 reactors totaling 63,000MW. Of its typical annual nuclear generation of 430,000GWh, France exports between 60,000GWh and 80,000GWh per year to Belgium, Germany, Italy, Spain, Switzerland and the UK. As an aside it’s really ironic that some of these countries have rather strong anti-nuclear policies.

 

The beginnings of France’s nuclear industry

 

The history of France’s nuclear power industry seems closely connected (in fact almost indistinguishable) from its nuclear weapons program after WW2, and appeared to stumble along until the 1st oil shock of 1973. Around this time France realised that it was short on indigenous energy resources but very strong in heavy engineering capability. As a result Electricité de France (EDF) installed 56 reactors by about 1990.

 

Current policy positions

 

Public opinion in France is very supportive of nuclear power, and seems to have taken less of a beating from the environmental movement than the nuclear policies of other European countries.

 

At an official level, France’s energy policy explicitly acknowledges the importance of nuclear power in securing energy supplies. This importance was recently re-affirmed by the establishment of a top-level council of ministers and officials to specifically drive nuclear initiatives. Curiously enough, nuclear energy has had historical support from France’s political left, which is in distinct contrast to Germany and Sweden.

 

UK – securing Britain’s electricity supplies

 

Introduction

 

The importance of natural gas in filling Britain’s emerging electricity supply gap has been a common theme of Pipes & Wires over recent months. This article notes the emergence of 3,800MW of gas-fired generation and examines the security of supply issues around that generation.

 

The new power stations

 

The new power stations are...

 

·       Npower received approval to build a 2,000MW combined-cycle plant at Pembroke.

 

·       Centrica received approval to build a 1,020MW combined-cycle plant at King’s Lynn.

 

·       Powerfuel plans to build an 800MW combined-cycle plant at Yorkshire by 2012.

 

Security of gas supply

 

One of the salient features to have emerged from the debate around the next generation of nuclear stations is the critical role that gas-fired generation will play over the next few years between the closure of several large coal-fired stations and the new nuclear stations coming on stream. A key reason for this is the short time to construct and commission a gas-fired station. However this reliance on gas-fired plant does seem puzzling given that the UK’s gas supplies seem far from secure ... the UK is more and more dependent on piped gas from Russia that is increasingly subject to interruption so it will be interesting to see just how well these gas-fired stations will fill the gap.

 

US – Maryland seeks to re-regulate

 

Introduction

 

Long-time readers might remember that Pipes & Wires #71 examined the possibility of using the Baltimore Metropolitan Council’s reservoirs to generate peak MW’s. That article also noted that as part of the election campaign for Governor, unsuccessful candidate Douglas M. Duncan wanted to re-regulate Maryland’s power industry “so that customer bills would automatically return to pre-deregulation levels”. This article examines 2 cross-filed bills that were introduced to the Maryland legislature in February 2009 requiring a return to a regulated market that seemed to be underpinned by a belief that reregulation will magically lower power prices.

 

Key features of the bills

 

The 2 bills are...

 

·       The Public Service Commission – New Electric Generation Facilities – Rate Regulation & Contracts was filed as Senate Bill 844 cross-filed with House Bill 1530. These bills would broadly require electric utilities to file long-term development plans with the Public Service Commission (PSC), require the PSC to consider those plans, empower the PSC to instruct an electric utility to build new generation, and state an intended return to a regulated market.

 

·       The Maryland Electricity Reregulation And Energy Independence Act 2009, which was filed as House Bill 1312 cross-filed with Senate Bill 795. The broad provisions of these bills are similar to SB844 and HB1530.

 

Passage of the bills

 

As of late April 2009 the passage of the bills is as follows...

 

·       SB844 passed its third reading 27 votes to 19 on 30th March, whilst HB1530 was withdrawn after receiving an unfavorable report by the Economic Matters committee.

 

·       HB1312 was withdrawn after an unfavorable report by the Economic Matters committee, whilst SB795 had only progressed to its first reading.

 

So although SB844 passed through the Senate successfully, it stalled in the House and had not progressed any further when the General Assembly adjourned on 13th April. This means that the bills are technically dead and will need to be reintroduced in the next legislative session.

 

Pipes & Wires comments

 

If we go back to what appears to be the underpinning motivation for these bills (ie. that reregulation will magically reduce electric tariffs to their pre-deregulation level), I think there will be some surprises. Sure the creation of a wholesale market which has then faced a short-fall of generation capacity has probably contributed to the tariff increases (and it remains to be seen whether instructing utilities to build new capacity will fix that issue), but the whole approach does seem to overlook the significant increases in coal and gas prices over the last 10 years. Like most things, time will tell.

 

Legal decisions

 

NZ – judicial review of the 400kV decision

 

Introduction

 

Most of us can recall only too well the controversy around the Electricity Commission’s decision to approve an amended version of Transpower’s proposed 400kV line from Whakamaru to Otahuhu. This article examines the judicial review of that decision sought by New Era Energy.

 

What exactly is a judicial review ?

 

Broadly speaking, a judicial review is a process in which the High Court reviews the exercise of power, typically by a government agency or local authority. A judicial review is usually restricted to matters of process rather than substance. Because it is process focused, a successful judicial review would normally only result in the Court ordering the decision-maker to reconsider its decision and it would be rare for the Court to ever substitute its own decision for that of the original decision-maker (ie. judge on issues of substance).

 

The Commission’s decision

 

In January 2007, the Electricity Commission announced that it intended to approve an amended version of Transpower’s proposed 400kV line. This decision was confirmed as final in June 2007, and was a reversal of the Commission’s previous decision to decline the originally proposed line.

 

What exactly was New Era Energy seeking ?

 

New Era Energy believed that the Commission did not adopt proper and fair processes in reaching its decision of January 2007, and wanted the High Court to set aside that decision. The basis of New Era Energy’s claim included illegality, irrationality, pre-determination & bias, and mistake of fact.

 

The High Court’s decision and New Era’s response

 

In a ruling released in early May 2009, the High Court turned down New Era’s request for a judicial review, rejecting the claim on all grounds and contemplating costs against New Era. Subsequently, in mid-May 2009 New Era announced that it would appeal the High Court’s decision.

 

A bit of light reading…

 

Book review – “Connecting The Country”

 

Helen Reilly’s latest book “Connecting The Country” is a history of NZ’s national grid from 1886 to 2007 that interestingly enough splits into the development of the AC and DC systems. Filled with photos, anecdotes and witty stories this is a really worthwhile read.

 

Order your copy from Transpower’s web site … cost is $60 incl. GST.

 

Wanted – old electricity history books

 

If anyone has an old copy of the following books (or any similar books) they no longer want I’d be happy to give them a good home…

 

·       White Diamonds North.

 

·       Northwards March The Pylons.

 

·       A Jubilee History Of The Auckland Electric Power Board (1972).

 

Assorted cool stuff

 

CapEx – general interest stuff

 

Levels of service and their impact on CapEx

 

This presentation was made at the Infrastructure CapEx Summit in November 2008. If you’d like a copy, pick here.

 

Upsizing – the other half of the hidden side of CapEx

 

This presentation was made at the Electricity Engineer’s Association conference in June 2008. If you’d like a copy, pick here.

 

Getting the CapEx right in the infrastructure sectors

 

This presentation was made at the NZIGE Spring Technical Seminar in September 2007. If you’d like a copy, pick here.

 

Renewals – (half) the hidden side of CapEx

 

This presentation was made at the Electricity Networks Asset Management Summit in November 2007 on the broad topic of asset renewals. If you’d like a copy, pick here.

 

PAS 55 – the emerging standard for asset management

 

To find out more about improving your asset management activities through adopting the emerging global standard for asset management PAS 55-1:2004 pick here or call Phil on +64-7-8546541, or to request a Slide Show on implementing PAS 55-1 pick here.

 

Website promoting best practice CapEx

 

Utility Consultants is pleased to announce the release of a specialist website dedicated to promoting best practice CapEx policies, processes and planning in the infrastructure sectors.

 

Assorted conference papers

 

Utility Consultants has recently presented the following conference papers which are available upon request…

 

·         “Tariff control of Pipes & Wires utilities – where is it heading??” – presented at the NZIGE Spring Technical Seminar, October 2006.

 

·         “Setting service levels for utility networks” – presented at the Electricity Network Asset Management Summit, November 2006.

 

House-keeping stuff

 

Opt out from Pipes & Wires

 

Pick this link to opt out from Pipes & Wires. Please ensure that you send from the email address we send Pipes & Wires to.

 

Disclaimer

 

These articles are of a general nature and are not intended as specific legal, consulting or investment advice, and are correct at the time of writing. In particular Pipes & Wires may make forward looking or speculative statements, projections or estimates of such matters as industry structural changes, merger outcomes or regulatory determinations.

 

Utility Consultants Ltd accepts no liability for action or inaction based on the contents of Pipes & Wires including any loss, damage or exposure to offensive material from linking to any websites contained herein.