Pipes & Wires

THE JOURNAL OF ENERGY & INFRASTRUCTURE THOUGHT LEADERSHIP

Issue 79 – February 2009

 

From the director…

Welcome to Pipes & Wires #79. This issue sees a real focus on competition and regulatory policy shifts in Europe, and also examines some regulatory matters in Australia. So, a short introduction this month, but hopefully some deep reading…

 

About Utility Consultants

 

Utility Consultants Ltd is a management consultancy specialising in the following aspects of energy and infrastructure networks…

 

·      Mergers & acquisitions

 

·        Asset management

·      Strategic studies

 

·        Financial analysis

·      Economic & structural regulation

·        Risk management

 

To be sent a detailed profile of recent projects, pick this link.

 

Competition policy

 

UK – OFGEM concludes its investigation

 

Introduction

 

Pipes & Wires #70 discussed OFGEM’s investigations into allegations that ScottishPower and Scottish & Southern Energy had abused a dominant position in an electricity market that arose because of a transmission constraint. This article considers OFGEM’s findings which were released in mid-January 2009.

 

Background

 

The basis of this matter is that under some situations, electricity transmission from Scotland into England can become constrained. OFGEM believed that both SP and S&SE took advantage of this situation by increasing their prices. The legal position in this matter is very clear … both Article 82 of the EC Treaty and Section 18 of the Competition Act 1998 prohibit a business holding a dominant position in a market from abusing that position. OFGEM initiated its investigation under s18.

 

The accusations

 

OFGEM’s accusation (which arose from a formal complaint) was two-fold…

 

·       Capacity was withheld from the wholesale forward market.

 

·       That same capacity was used to supply balancing power to National Grid at excessive prices.

 

For the avoidance of doubt, it is emphasized that the holding of a dominant position is not an offense (but rather it is the taking advantage of such a position that is an offence).

 

OFGEM’s concerns & conclusions

 

OFGEM expressed concern over the following two matters…

 

·       That both SP and S&SE’s output seemed much more expensive than comparable generators at the time of the constraint.

 

·       That SP, S&SE or both may have behaved in a manner that exacerbated or even caused the constraint.

 

However, in its letter of 19th January 2009, OFGEM concluded that the likelihood of making an infringement finding was low (although not negligible). OFGEM also concluded that pursuing the matter would not be an efficient use of resources, especially given that the matter would be likely to be addressed by the Transmission Access Review.

 

So in conclusion, OFGEM decided to close the matter with no further action, whilst reserving the right to re-open the matter “should circumstances warrant action”.

 

Belgium – limiting Electrabel’s market share

 

Introduction

 

Requiring merger concessions is a very common instrument used to control levels of dominance in markets. This article examines recent happenings pursuant to the Pax Electrica 2 agreement between Electrabel and the Belgian Government.

 

The background to Pax Electrica 2

 

Pax Electrica 2 is an agreement between Electrabel and the Belgian Government under which part of the output of Electrabel’s 6,000MW of Belgian nuclear capacity would be made available to competing third parties. Under the Pax, Belgian energy company SPE (of which Gaz De France owned 25.5%) would be given 535MW of power off-takes.

 

The reason for the Pax was the concentration of ownership created by the merger of Suez and GDF. Suez subsidiary Electrabel had a 64% share of the retail electricity market, but the complicating factor was that a further 21% of the electricity market held by Luminus and Citypower were effectively controlled by GDF. This would’ve led to the merged GDF Suez controlling about 85% of the electricity market.

 

Recent happenings

 

In December 2008 Electrabel agreed to sell 1,700MW of Belgian generating capacity and power procurement rights to E.On, giving E.On about 12% of the Belgian electricity market. In return, E.On agreed to sell 800MW of German generating capacity and a further 700MW of German power procurement rights to Electrabel.

 

As an aside to the Electrabel deal as part of its EU anti-trust settlement, E.On also agreed to sell 500MW of capacity to German rival EnBW.

 

UK – policy issues behind the Brit Energy sale

 

Introduction

 

The cyclical booms and busts of British Energy have been a long-time topic of Pipes & Wires. This article rounds out Electricité De France’s (EDF) recent acquisition of Brit Energy by noting the European Commission’s (EC) required concessions and considering some of the policy issues involved.

 

The concessions

 

The EC, under the EU Merger Regulations, has required the following concessions to be made…

 

·       EDF must sell its Sutton Bridge Power Station.

 

·       Brit Energy must sell its Eggborough Power Station.

 

·       The merged entity must sell specified minimum volumes into the British wholesale electricity market.

 

·       The merged entity must sell a site at either Dungeness or Heysham that would be suitable for building a nuclear power station.

 

·       The merged entity must terminate 1 of its 3 grid connection agreements with NGC at Hinkley Point.

 

The policy issues

 

As part of its examination of the proposed sale, the EC concluded that although the merged entity would not have an excessive market share, concerns would’ve arisen in 4 broad areas…

 

·       The combination of Brit Energy’s base-load plant and EDF’s flexible plant could’ve created the potential for the merged entity to game the market by withdrawing plant.

 

·       The balancing of EDF’s short position and Brit Energy’s long position could’ve led the merged entity to sell to its own retail market rather than through the wholesale pool.

 

·       Most of the suitable sites for building the next generation of nuclear plants were at existing Brit Energy or EDF sites, which could limit the ability of a third party to build the next nuclear plant.

 

·       The capacity connection rights to the grid that would be held by the merged entity at Hinkley Point would be in excess of its planned capacity expansion and could therefore exclude a competitor from connecting.

 

Brit Energy and EDF provided both an initial and a revised package of concessions to the EC to mitigate its concerns. The EC concluded that the revised concession package was sufficient, and gave its approval subject to those concessions being implemented.

 

Some thoughts from the editor

 

Efficient operation of markets is the guiding mantra of most, if not all, competition regulators, and a key part of that is ensuring that no single player achieves positions of market dominance. However, little obvious thought seems to have been given to effective operation of markets, and that the long-term well-being of customers depends on sufficient investment in new capacity. Pipes & Wires first examined this issue back in August 2004 (funnily enough that issue also examined Brit Energy’s tough times) and expressed the thought “what if the only parties willing to invest are those that would be prohibited from investing due to competition law”. As the UK faces an expected significant short-fall of capacity perhaps the effectiveness of markets needs to be revisited.

 

Energy markets

 

Germany – regulating competitive assets

 

Introduction

 

Most of us accept the need for regulating pipes & wires that are not subject to competition, but would almost certainly question tariff regulation of such assets that are subject to market disciplines. This article examines the recent decision by German gas transmission operator Wingas Transport to abandon the proposed 500km Süddeutsche Erdgasleitung (SEL) pipeline across southern Germany because the federal energy regulator Bundesnetzagentur has decided that the SEL’s tariffs would be set by regulation and not by market forces.

 

The proposed SEL pipeline

 

The SEL was proposed to run between the Lampertheim gas hub and Burghausen, which is becoming an increasingly important trading and storage node for imported Russian gas. The total investment was expected to be about €600m.

 

The regulatory framework

 

The underpinning regulatory framework is the EU Gas Directive (98/30/EC), which required member states to comply with the requirements of the Directive no later than 1st July 2004. This was overtaken by Directive 2003/55/EC in June 2003, which in conjunction with Regulation 1755/2005, provides for national regulators to fix transmission tariffs.

 

Wingas’ argument

 

Wingas’ argument is that the SEL would be subject to competition, therefore its tariffs should be set by the market, and not by regulation.

 

The Bund’s argument

 

In a media statement, the Bund seemed puzzled by Wingas’ argument that such pipelines are uneconomic, especially when it had recently granted a WACC of 9.29% which it claimed was an attractive figure in the current climate. However this doesn’t appear to address Wingas’ argument that a competitive asset shouldn’t have its tariffs (and by implication, it’s WACC) set by regulation, no matter how apparently attractive.

 

Energy policy

 

Sweden – re-thinking the nuclear phase-out

 

Introduction

 

Shifts (or even lurches) in nuclear policy are no stranger to the pages of Pipes & Wires, especially as many seem to be questioning the scientific basis of climate change and concern mounts over declining security margins. Following on from Germany’s back-peddle (discussed in Pipes & Wires #77), Sweden’s announcement in early February 2009 that it would allow replacement of existing reactors didn’t come as a great surprise.

 

Background

 

Sweden decided way back in 1980 that it would migrate away from nuclear power as a result of a referendum held the previous year. This resulted in a two-fold decision…

 

·       There would be no further nuclear plants.

 

·       The phase-out of existing plant should be completed by 2010.

 

I guess for those of us who were still in short pants back in 1980, it would be important to understand the hysteria that was whipped up over Three Mile Island (and again over Chernobyl in 1986). In 1997 the Government attempted to accelerate the closure of the 2 reactors at Barsebäck to 1998 and 2001 respectively, but these were operated until 1999 and 2005. However the Government’s decision of 1998 not to build any more hydro’s (to protect water resources) was considered to have set the phase-out back to 2045.

 

The latest policy movements

 

The Government’s policy announcement of 5th February 2009 said that it intended to construct new nuclear plants as well as scrap the phase-out of existing plants to reduce Sweden’s dependence on fossil fuels and reduce emissions.

 

This policy shift is expected to create an interesting dynamic amongst policy makers as Sweden takes up the rotating EU presidency in mid-2009 and oversees a major climate change forum. It does need to be said that nuclear power may not be the answer to the converging crises of emissions, fossil fuel dependence and dwindling security margins, but at last we are now having the debate.

 

Regulatory policy

 

Aus – the AER takes over from the ESC

 

Introduction

 

Pipes & Wires first examined the consolidation of Australia’s 13 energy regulators way back in March 2004. After almost 5 years of progress this article takes a quick look at the hand-over from the Essential Services Commission to the Australian Energy Regulator that occurred on 1st January 2009.

 

Background

 

Readers may recall that one of the Parer Review’s findings was that the Australian energy sector was over-regulated which was causing barriers to new investment. One of the key underlying issues was the multi-dimensional transformation of the traditional boundaries of vertically disaggregated, state-owned utilities that operated in only 1 state into consolidated, multi-state, private utilities having to deal with multiple regulators.

 

The Victorian transition

 

At the very outset it was recognised that the move from multiple regulators to a single regulator would need to be a gradual process, and the Victorian hand-over represents another step in that process.

 

The legal basis for the hand-over is set out in the National Electricity (Victoria) Act 2005 which transferred the administration of the economic regulatory framework for electricity distribution from the ESC to the AER effective 1st January 2009. The ESC will continue to administer the licenses for the 5 Victorian DNSP’s and the regulation of the electricity retail businesses.

 

The AER rolls up its sleeves and gets stuck in

 

The AER has added the Victorian distribution re-set on 1st January 2011 to its pile of stuff to do. It is currently consulting on its preliminary Framework & Approaches views and expects to release its final paper in May 2009. That will pave the way for the 5 Victorian DNSP’s to submit their Proposals at the end of November 2009.

 

UK – update on 5th DPCR

 

Introduction

 

Pipes & Wires has been closely following the policy level development of the 5th electricity distribution price control in the UK. Following on from OFGEM’s thoughts in November 2008 (discussed in Pipes & Wires #77), this article examines OFGEM’s Policy Paper that was released in December 2008.

 

Background

 

OFGEM’s November 2008 paper set out a number of thoughts that signaled a shift in policy direction. The most significant of these thoughts included…

 

·       Incentivising outcomes in excess of stated requirements.

 

·       Incentivising replacement of dumb assets with smart assets.

 

·       Mimicking the returns on equity that are available to the competitive sectors.

 

Summary of the Policy Paper

 

The December 2008 Policy Paper clearly sets out 3 key objectives for DPCR5…

 

·       Encouraging DNO’s to help tackle climate change.

 

·       Strengthen non-network aspects of customer service (such as call centers and new connections).

 

·       Incentivising efficient, least-cost investment in reliable, secure networks.

 

OFGEM believes that DPCR5 will have been successful if firstly the regulatory settlement provides reasonable rewards for meeting those objectives, and secondly if the DNO’s that perform the highest against those objectives receive the greatest rewards. Key themes of the December 2008 Policy Paper include…

 

·       How DNO’s can contribute to assisting the UK’s climate change initiatives, as well as reducing their own carbon footprint.

 

·       Identifying aspects of customer service that could be strengthened and developing existing mechanisms and new initiatives to encourage DNO’s to respond to those initiatives.

 

·       A shift from measuring network cost performance by inputs to measuring by outputs, including some new thoughts on cost incentives.

 

·       OFGEM’s thoughts on WACC, RAV, taxes, pensions and issues affecting DNO’s financeability.

 

The next major step is expected in May 2009 when OFGEM will publish its methodology document and initial results.

 

Aus – reviewing the WACC

 

Introduction

 

Pipes & Wires #75 examined the Australian Energy Regulator’s planned review of the constituent components of the much-loved and all-important WACC. This article examines the AER’s proposed conclusions underlying a proposed reduction in nominal post-tax WACC from the current range of between 9.32% and 9.56% to a lesser figure of 8.60%.

 

Background

 

The National Electricity Rules (NER) provide for the AER to review the WACC parameters used in electricity distribution and transmission determinations. Reviews may be conducted at 5 yearly intervals, with the first review being completed by 31st March 2009. The AER set out a number of key issues that it wished to examine as part of that review

 

The AER’s proposed conclusions

 

The AER’s proposed conclusions include…

 

·       The nominal risk-free rate (Rf) shall be based on a moving average annualised yield on Commonwealth Government bonds having a maturity period that matches the term of the control period.

 

·       The time period during which the risk-free rate is to be calculated shall be a period proposed by the TNSP or DNSP that is as close as practically possible to the start of the control period , or some other period specified by the AER if it does not agree with the period proposed.

 

·       The equity beta (βe) shall be reduced from the current range of between 0.9 and 1.0 to a lesser figure of 0.8.

 

·       The market risk premium (MRP) shall remain unchanged at 6.0%.

 

·       The ratio of debt to (debt + equity) shall remain unchanged at 0.6.

 

·       The benchmark credit rating shall increase from BBB+ to A-.

 

·       The assumed utilisation of imputation credits (γ) shall increase from 0.to a greater figure of 0.65.

 

The AER expects to release its final statement by 31st March 2009.

 

Applicability of the reviewed WACC parameters

 

The outcomes of this review will apply only to determinations for which the proposal is submitted after 1st March 2009 and before 1st April 2014, viz…

 

·         The outcome of the review will apply to the forthcoming SA, Queensland, Tasmanian and Victorian distribution determinations.

 

·         The outcome of the review will not apply to the forthcoming ACT and NSW distribution determinations or to the forthcoming NSW and Tasmanian transmission determinations.

 

Disclaimer

 

Readers should read all relevant AER publications in their entirety. Utility Consultants Ltd nor its shareholder or directors shall be responsible for any action or failure to act based on this article.

 

Portugal – promoting investment

 

Introduction

 

Recent regulatory policy has given much attention to the need to promote new investment in pipes & wires, especially around the simple fact that investors take their prompts from the regulators view of WACC. Recent issues of Pipes & Wires have noted the introduction of two-tier WACC’s in France and Germany to promote new investment … this article follows on by noting a similar arrangement in Portugal.

 

Previous instances of two-tier WACC’s

 

The following two previous instances of two-tier WACC’s have been identified…

 

·       In early 2007, the Commission de Regulation de l’Energie (CRE) allowed Gaz De France (GDF) subsidiary GRTgaz to increase its cost of capital by 300 basis points above the currently permitted 8.5% for 10 years to incentivise an additional €280m of CapEx to reduce constraints between its northern, eastern and western balancing zones.

 

·       In mid-2008, the Bundesnetzagentur decreed a pre-tax cost of equity of 9.29% for new investments and 7.56% for legacy investments in the German electricity distribution sector. The Bund has deliberately introduced a two-tier cost of equity to incentivise new investment, which is expected to be about €8.6b industry-wide over 3 years.

 

The proposed two-tier WACC in Portugal

 

The Portuguese energy regulator, Entidade Reguladora Dos Serviços Energéticos (ERSE), has approved an increased WACC of 9.05%, up from 7.55% for the current 3 year regulatory control period for new investments by transmission grid operator Redes De Confiança (REN), and will also allow new investments to be valued at standard cost (instead of actual cost) on an ex-ante basis.

 

Presumably these incentives have worked as REN recently announced that it would lift this coming year’s investment level by about 60%.

 

Mergers, acquisitions & take-overs

 

Holland – progress on the Nuon sale

 

Introduction

 

Structural regulation usually always prompts ownership reshuffling. Against a back-drop of unbundling lines & energy in Europe, this article considers the possible sale of Dutch utility Nuon to Swedish utility Vattenfall. This follows its failure to work out a merger with fellow Dutch utility Essent and Essent’s subsequent acquisition by RWE.

 

Emerging details of the possible Nuon sale

 

Recent media reports indicate that Vattenfall has a strong interest in Nuon, but the deal is far from concluded. After missing out on Essent, Vattenfall seems keener than ever to expand its horizons.

 

The strategic drivers

 

Moving from being a vertically-integrated utility in a well-defined geographical area such as a state or country to what seems to be a hodge-podge of activities across multiple jurisdictions takes a bit of understanding. Certainly in the case of the European utilities there seem to be four strategic drivers…

 

·       The requirement to unbundle lines & energy, which is driving utilities from being “tall & narrow” to “wide and low”.

 

·       Merger concessions such as Pax Electrica 2 and the conditions on EDF’s acquisition of Brit Energy (both discussed in Pipes & Wires #79) which often requires chunks of generation or power purchase rights to be on-sold to third parties to prevent market dominance.

 

·       Privatisations, albeit moving more slowly these days, present out-of-town players with the opportunity to enter new markets.

 

·       The opportunity to extract synergies by reshuffling portfolios of assets.

 

Pipes & Wires will make further comment on the Nuon sale if and when further details emerge.

 

Assorted cool stuff

 

CapEx – general interest stuff

 

Levels of service and their impact on CapEx

 

This presentation was made at the Infrastructure CapEx Summit in November 2008. If you’d like a copy, pick here.

 

Upsizing – the other half of the hidden side of CapEx

 

This presentation was made at the Electricity Engineer’s Association conference in June 2008. If you’d like a copy, pick here.

 

Getting the CapEx right in the infrastructure sectors

 

This presentation was made at the NZIGE Spring Technical Seminar in September 2007. If you’d like a copy, pick here.

 

Renewals – (half) the hidden side of CapEx

 

This presentation was made at the Electricity Networks Asset Management Summit in November 2007 on the broad topic of asset renewals. If you’d like a copy, pick here.

 

PAS 55 – the emerging standard for asset management

 

To find out more about improving your asset management activities through adopting the emerging global standard for asset management PAS 55-1:2004 pick here or call Phil on +64-7-8546541, or to request a Slide Show on implementing PAS 55-1 pick here.

 

Website promoting best practice CapEx

 

Utility Consultants is pleased to announce the release of a specialist website dedicated to promoting best practice CapEx policies, processes and planning in the infrastructure sectors.

 

Assorted conference papers

 

Utility Consultants has recently presented the following conference papers which are available upon request…

 

·         “Tariff control of Pipes & Wires utilities – where is it heading??” – presented at the NZIGE Spring Technical Seminar, October 2006.

 

·         “Setting service levels for utility networks” – presented at the Electricity Network Asset Management Summit, November 2006.

 

Conferences & events

 

The Fast-tracking National Infrastructure Summit (Wellington, 27-28 April)

 

With an RMA overhaul, local body governance reform, and increased funding for critical projects all in the pipeline, the stark reality is that the national infrastructure landscape is set to evolve rapidly under the new Government. The question is - how will you adapt to these changes?

 

Conferenz’s Fast-tracking National Infrastructure Summit will outline all of the changes and their likely effects on your organization…

 

·       The need for cross-industry co-ordination in infrastructure policy

·       Planning for the new fast-tracked RMA consultation process

·       Prospects for local body governance

·       Defining the criteria for “projects of critical national importance”

·       Examining different funding mechanisms - how will PPPs fit in under the new Government?

 

Make the investment and get ahead of the curve. Register now by phoning Conferenz on (09) 912 3616, Email register@conferenz.co.nz or Register Online at www.conferenz.co.nz

 

House-keeping stuff

 

Opt out from Pipes & Wires

 

Pick this link to opt out from Pipes & Wires. Please ensure that you send from the email address we send Pipes & Wires to.

 

Disclaimer

 

These articles are of a general nature and are not intended as specific legal, consulting or investment advice, and are correct at the time of writing. In particular Pipes & Wires may make forward looking or speculative statements, projections or estimates of such matters as industry structural changes, merger outcomes or regulatory determinations.

 

Utility Consultants Ltd accepts no liability for action or inaction based on the contents of Pipes & Wires including any loss, damage or exposure to offensive material from linking to any websites contained herein.