From the
editor’s desk…
Welcome
to Pipes & Wires #144 after a few months break. This issue starts by
examining 2 large mergers in the US and the privatisation of TransGrid in
Australia. We then look at 2 cost of capital determinations in NZ, and then
look at a wide range of energy policy and market issues including the UK’s
declining security of supply, the recently released Tasmanian energy strategy
and the likely future of hydro in the US. So … happy reading.
Matters for attention in NZ
Readers’
attention is drawn to the following matters…
· The Select Committee on the Health & Safety Reform Bill
has reported back.
· Changes to the requirements for connecting embedded generation to distribution.
· Increasing interest in ISO 55000:2014 in regard to asset management practices and systems, and
the associated withdrawal of BSI PAS 55:2008.
· Revised standard NZS 7901:2014 for Safety Management
Systems.
Interesting fact…
Most
of us are aware that increasing penetration of air conditioners is requiring
summer peaking plant. Readers might be surprised to learn that the world’s
first summer peaking generation plant was built as far back as 1942 (back in
the day when installing air conditioning literally cost a fortune).
Mergers & acquisitions
US – progress on the We Energies – Integrys merger
Introduction
Pipes & Wires #141 and #143 examined of We Energies $9.1b bid for Integrys Energy
Group and noted a number of regulatory approvals that were required. This
article notes the conclusion of the regulatory approvals process.
The proposed merger
The
proposed merger is a combined stock, cash and assumption of debt deal totaling
$9.1b which values Integrys at $71.47 per share. The merged company would
supply 1,490,000 electric customers and 2,445,000 gas customers and would be
headquartered in Milwaukee.
Progress on the required approvals
Progress on the
required approvals is as follows…
Regulator |
Progress on
approval |
Federal Energy Regulatory Commission. |
Approved in
mid-April 2015, stating that there would be no cross-subsidy of a non-utility
associate company. |
Wisconsin Public Service Commission. |
Approved in late
April 2015, with the major conditions being that any profit over and above
the authorised return on equity would need to be returned to We Energies
customers, and a gas-fired generation plant proposed by We Energies
subsidiary Wisconsin Public Service is to be abandoned. |
|
Approved in June
2015, with a major condition being a 2 year tariff freeze. |
Michigan Public
Service Commission. |
Approved in
mid-April 2015. |
Minnesota Public Utilities Commission. |
Approved in June
2015. |
The completion of the regulatory approvals process
concludes Pipes & Wires analysis of this merger.
US - the Exelon-Pepco merger nears
final approval
Introduction
Previous
issues of Pipes & Wires have examined Exelon’s proposed acquisition of Pepco. This issue notes two further regulatory approvals by the Delaware
and Maryland Public Service Commissions.
Key features of Exelon’s offer
Exelon
has made a $6.8b all-cash offer of $27.25 per Pepco share, which represented a
24.7% premium to Pepco’s closing price on the announcement day.
Status of the required approvals
The
status of the regulatory approvals is…
Regulator |
Current
status of approval |
Federal Energy Regulatory Commission. |
Approved
20th November 2014. |
District of Columbia Public Service
Commission. |
Application
filed on 18th June 2014. |
Delaware Public Service Commission. |
Approved
in May 2015, but with conditions including a package of benefits worth $42m
to Delaware and Delmarva Power customers. |
Maryland Public Service Commission. |
Approved
in May 2015, including 46 conditions that included a $100 credit to all
Maryland and Delmarva Power customers, improved fault response and
establishment of a $43m energy efficiency fund. |
New
Jersey Board of Public Utilities. |
Approved
on 11th February 2015, with the 2 conditions that include a
settlement being reached between Exelon, Pepco, the Board and the Independent
Energy Producers of New Jersey that included provisions for $15m of
efficiency gains for customers of Atlantic
City Electric, and establishing a fund of $62m to provide rebates to
Atlantic City Electric customers. |
Virginia
State Corporation Commission. |
Approved
8th October 2014. |
Pipes
& Wires will comment further as the (Washington) DC Public Service
Commission decided whether or not to approve the deal.
Industry restructurings
Aus – the race is on for TransGrid
Introduction
The (estimated)
$30b sale of poles and wires in the Australian state of New South Wales (NSW)
recently commenced with a formal invitation for expressions of interest in the
long-term lease of the state’s electricity transmission business TransGrid. This article examines the likely bidders and the next steps in the
process.
A bit about TransGrid
TransGrid owns and
operates the electricity transmission grid throughout the state of NSW, and is
100% owned by the NSW government. TransGrid operates 12,900km of lines and 99
substations and switching stations at 132kV, 220kV, 330kV and 500kV.
What is actually on offer ??
What is being
offered is a 99 year lease of the TransGrid assets, presumably similar to the
200 year lease of ElectraNet in South Australia.
The likely bidders
Initial likely
bidders were thought to include…
· Hastings Funds
Management in association with Spark
Infrastructure, the Abu Dhabi Investment Authority, the Canadian Pension Fund and Wren House Infrastructure.
· The Australian Super Fund.
· State Grid
Corporation of China in association with Macquarie Bank.
· Singapore Power through AusNet Services.
Expected bids
Short-listed
bidders are expected to offer between 1.2x and 1.5x TransGrid’s regulatory
asset base (RAB) of $6b, with interest in the fiber assets as a source of
revenue growth.
Next steps
Expressions of
interest closed on 14th July, and binding bids are due in
mid-September. Final bids are due in November, so Pipes & Wires will make
further comment then.
People in power
This
series of historical interest articles follows on from a similar series a few
years ago, and examines the lives and achievements of electrical pioneers that
were born in the last few decades of the 1800’s.
Thomas W.
Martin builds an electric empire
Birth, early years and education
Thomas Wesley
Martin was born in Scottsboro, Alabama in 1881. After attending prep school
until the age of 17, Thomas attended the University Of
Alabama where he completed a law degree in 1901. His pursuit of law was not
surprising as his father William Logan Martin was a prominent lawyer who was
appointed Alabama’s attorney general in 1889. Thus began a life in which young
Thomas was in the company of several prominent and influential lawyers.
The law practice in Montgomery
In 1901 Thomas
began practicing law in Montgomery, Alabama in his fathers’ law practice of
Tyson, Wilson & Martin in which young Thomas was introduced to Massey
Wilson who got Thomas working on the legal issues of hydro-electric dam
construction. Again, this seems to have been a very fortuitous start for Thomas
as his fathers’ partners were amazingly well politically connected ... John
Tyson had been a City Councillor, an Alabama Supreme Court judge, and an
Alabama Congressman, whilst Massey Wilson was a former Alabama Attorney
General. It appears that Thomas then left his father’s practice around about
1903 to become Alabama’s Assistant Attorney General until about 1911.
The introduction to things electric
Around 1912 James
Marshall from Massachusetts bought the rights to develop a hydro dam on the Coosa River from Alabama Power, having retained Thomas the previous year as legal
counsel. The dam became operational in 1914 and was the starting point for
Alabama’s electric supply industry.
Thomas’ career continues as Alabama Power expands
Thomas served as
legal counsel for the emerging Alabama Traction, Light & Power until James
Mitchell’s death in 1920 whereupon Thomas became president. Many initiatives
began during Thomas’ presidency…
· The beginning of a rural
electrification program.
· The establishment of a
hydrology laboratory in Birmingham to assist hydro dam design.
· The completion of the Mitchell Dam on the Coosa River in 1921.
· Establishment of an
economic development unit to attract new industry to the state.
· Funding a program at Auburn
University to determine how electricity could improve farm yields.
On a wider scale,
Thomas also encouraged electrical inter-connection between Alabama and Georgia
that resulted in the formation of the Southeastern Power & Light holding
company that eventually included Mississippi Power, Georgia Power, South Carolina Power and Gulf Power. Around the time of the Wall Street crash, SP&L became investor
owned and amalgamated with Midwestern Utilities and the Tennessee Electric
Power Company to form Commonwealth & Southern.
The formation of Southern Company
Readers with long
memories (or a bent for history) might remember from Pipes & Wires #55, #97, and #98 that C&S played a significant role in shaping the investor-owned
electricity sector before being broken up as a result of the Public Utility Holding Company Act 1935. After being busted up because of their non-contiguous
networks, Thomas took a lead to form the Southern Company which in 1949 became
the holding company for the 4 big electric companies Alabama Power, Georgia Power, Mississippi Power and Gulf Power.
Later years
Thomas retired as
president of Southern Company and Alabama Power in 1949, but remained
influential with both electrical matters and civic affairs until his death in
1964.
Regulatory decisions
NZ – gas under pressure
Introduction
The Commerce
Commission recently released its cost of capital determination for any customised price-quality path that
Maui Developments may make for its gas transmission service until June 2016. This article examines the key features of that determination.
Regulatory framework
The regulatory
framework is set out s5.3 of the Gas Transmission Services Input Methodology Determination 2012, whilst the wider framework for setting WACC’s is s52T of the Commerce Act 1986 which sets out the matters covered by the Input Methodologies.
Key features of the gas transmission WACC
Key features of
the gas transmission Vanilla WACC include…
Vanilla WACC
period |
Mid-point |
67th
percentile |
3 years |
6.63% |
7.16% |
4 years |
6.62% |
7.15% |
5 years |
6.71% |
7.23% |
NZ – determining the WACC for electricity transmission
Introduction
The Commerce
Commission recently released its WACC determination that will apply to electricity transmission grid
operator Transpower for the year ending 30th June 2016. This article examines the key features of that determination.
Regulatory framework
The regulatory
framework is set out in clauses 2.4.1 to 2.4.7 of the Transpower Input Methodologies Determinations 2012 (ref. NZCC 17). This is pursuant to Subpart 3 of Part of the Commerce Act 1986.
Key features of the WACC determination
Key features of
the Transpower WACC determination include…
|
25th
percentile |
Mid-point |
67th
percentile |
75th
percentile |
Vanilla WACC |
5.23% |
5.95% |
6.41% |
6.66% |
Post-tax WACC |
4.60% |
5.32% |
5.78% |
6.03% |
NZ - previous WACC decisions
Some
of the Commissions’ previous WACC decisions are as follows.
WACC
decision applies to |
Approx
date |
Mid-point
WACC |
75th
(or 67th) percentile WACC |
Vector
and Powerco gas pipelines for year ending 30th June 2016. |
July
2015 |
Vanilla
6.65%. |
Vanilla
75th percentile 7.46%. |
Transpower
for year ending 30th June 2016 |
July
2015 |
Vanilla
5.95%. |
Vanilla
67th percentile 6.41%. |
Maui
CPP application before June 2016 |
June
2015 |
Vanilla
6.63% to 6.71%. |
Vanilla
67th percentile 7.16% to 7.23%. |
All
electricity distribution for year starting on 1st April 2015. |
April
2015 |
Vanilla
6.02%, post-tax 5.37%. |
Vanilla
6.49%, post-tax 5.84%. |
Wellington
Airport for year starting on 1st April 2015. |
April
2015 |
Vanilla
6.93%, post-tax 6.71%. |
Vanilla
7.91%, post-tax 7.69%. |
Powerco
gas CPP application before April 2016. |
March
2015 |
Vanilla
6.70% to 6.72%. |
Vanilla
7.23% to 7.25%. |
Maui
Developments for 2016 disclosure year |
January
2015 |
Vanilla
7.08%. |
Vanilla
7.89%. |
Vector,
GasNet CPP application before December 2015. |
December
2014 |
Vanilla
7.11%, 7.14%, 7.22%. |
|
All
electricity CPP applications after 30th September 2014. |
September
2014 |
Vanilla
6.58%, 6.64%, 6.72%. |
|
Auckland,
Christchurch Airports for 2015 disclosure year. |
July
2014 |
Vanilla
7.64%. |
Vanilla
8.63%. |
Vector,
GasNet for 2015 disclosure year. |
July
2014 |
Vanilla
7.54%. |
Vanilla
8.35%. |
Transpower
for 2015 disclosure year. |
July
2014 |
Vanilla
6.83%. |
Vanilla
7.55%. |
Wellington
Airport for 2015 disclosure year. |
April
2014 |
Vanilla
7.70%. |
|
EDB’s
for 2015 disclosure year. |
April
2014 |
Vanilla
6.89%. |
|
Powerco
gas CPP applications before March 2015. |
March
2014 |
Vanilla
5-year 7.54%. |
Vanilla
5-year 8.35%. |
Maui
pipeline (gas transmission). |
January
2014 |
Vanilla
7.64%, post-tax 6.85%. |
|
Vector,
GasNet CPP applications before December 2014. |
December
2013 |
Vanilla
7.56%. |
|
All
CPP applications before 30th September 2014 |
September
2013 |
Vanilla
from 6.26% to 6.69%. |
Vanilla
from 6.97% to 7.41%. |
Transpower |
July
2013 |
|
Vanilla
6.85%, post-tax 6.17%. |
Vector
gas distribution, GasNet |
July
2013 |
|
Vanilla
7.65%, post-tax 6.97%. |
Auckland
& Christchurch airports |
July
2013 |
|
Vanilla
8.00%, post-tax 7.75%. |
All
electricity distribution |
April
2013 |
|
Vanilla
6.83%, post-tax 6.14%. |
Maui
pipeline (gas transmission) |
February
2013 |
|
Vanilla
7.46%, post-tax 6.80%. |
All
gas distribution and gas transmission DPP’s |
December
2012 |
|
Vanilla
6.63%. |
Vector,
GasNet CPP’s |
December
2012 |
Vanilla
6.39% (5 years). |
|
Powerco
gas distribution |
October
2012 |
Vanilla
6.83%, post-tax 6.12%. |
|
Energy policy & markets
UK – avoiding wide-spread blackouts
Introduction
Back
in May Pipes & Wires #143 examined the UK’s declining reserve capacity margin. Since
then National Grid has recently announced that the risk of blackouts for the
coming (northern) winter has increased since last winter. This article examines
this fundamentally important matter.
The decline in reserve capacity margin
The
reserve capacity margin for the 2011-12 winter was about 17%, a level
recognised as providing a prudent trade-off between black-out risk and
acceptable utilisation of capital. That margin fell to a whisker under 5% last
winter (2014-15) and was expected to fall to about 2% for the coming 2015-16
winter (in the absence of any prompt intervention) as 2,000MW of capacity at Barking,
Ferrybridge C and Littlebrook close.
The interventions
Two
key interventions are planned…
· National Grid will pay for generation plant to be kept on
standby. This will cost about £36m per year, and add about 50p to a monthly
domestic electric bill.
· Large users such as steel mills will be asked to curtail
demand during grid peaks.
The wider picture of why the reserve capacity margin is
falling
The
principal reason for the declining reserve capacity margin is that generation
capacity closures are not being matched by new capacity. Key reasons include…
· Closure of legacy coal-fired stations under the EU’s large combustion plant directive.
· Languishing wholesale prices that are making new capacity
uneconomic.
· The difficulty in obtaining certainty of forward prices for
the proposed new nuclear fleet (remember what a struggle it was to get 1
station across the line).
Restoring
the reserve capacity margin will therefore require price certainty for new
investors. Additional market mechanisms such as the capacity market will be
useful, but one way or another someone will have to build some serious
generation capacity.
Aus – the release of the Tasmanian Energy Strategy
Introduction
Following
the release of the Commonwealth Government’s Energy White Paper, the Tasmanian Government has recently released its own Energy Strategy entitled Restoring Tasmania’s Energy Advantage.
Vision and themes of the Tasmanian Energy Strategy
The
vision of the Strategy is “restore energy as a competitive advantage for
Tasmania”, along with 5 key themes…
· Delivering affordable energy at competitive and predictable
prices that are among the lowest in Australia.
· Empowering consumer choice.
· Ensuring an efficient energy sector that is
customer-focused.
· Utilising energy to facilitate State growth.
· Maximising Tasmania’s renewable energy opportunities.
Key
outcomes include planning a second Bass Straight cable and increasing
Tasmania’s hydro generation output by 10%.
The editor comments
The
above 5 themes are certainly very noble and worthwhile, but how might those
themes end up as tangible outcomes, principally lower and more predictable electricity
prices ? A few comments…
· One of the stated directions is to use renewable energy to
attract energy-intensive industries. That could prove very valuable for
industries like smelting and refining that need predictably priced electricity
(as long as the electricity supply is secure).
· It is expected that demand increases will prompt the private
sector to build new generation capacity. That will require predictable
long-term prices.
· The need to integrate a wide range of energies into a single
strategy, including gas and bio-mass.
· Managing forward prices will be critical. Languishing
wholesale prices dampen investment enthusiasm, but unless those low prices
carry through to retail prices, consumers don’t benefit.
So it
will be interesting to see how the implementation of this strategy actually
works out.
US – will hydro make a comeback ?
Introduction
There
is no doubt that hydro has been sidelined in the renewables debate, principally
because of the way it significantly alters natural waterways. This article
examines a recent Department of Energy report which suggests that hydro could make a comeback.
The key issues
The principal
issue with hydro tends to be opposition from environmental groups (and that is
certainly not unique to the United States). However, in amongst the
non-emitting generation, hydro has the key advantage that it can be stored in
bulk and its weather dependency is typically month-by-month (or even year-by-year)
rather than minute-by-minute.
The current state of hydro in the US
The US
has about 80,000 MW of hydro generation (excluding pumped storage), which
represents about 7% of installed capacity. This generation is heavily
concentrated, with 21,300 MW in Washington, 10,300 MW in California and 8,300
MW in Oregon … pretty much 50% of US hydro is concentrated on the west coast.
Additions
to the national hydro generation fleet appear to be large numbers of smaller
plants or improvements to existing plants, with only about 1,500 MW of
additional capacity being added between 2005 and 2013.
The expected trends
New
hydro (and pumped storage) capacity is expected to increase with about 5,000 MW
at various stages from concept to construction. So it would appear that hydro has
at least some future.
Asset strategy & management
UK – revising electricity security of supply standards
Introduction
Most
of us are familiar with the Engineering Recommendation (ER) P2 planning
standards for transmission and distribution network security. This article
examines the current review of P2 initiated by the Distribution Code Review
Panel.
The P2/5 and P2/6 standards
The
P2/5 standard was introduced in October 1978 to set out the percentage of
demand that should be restored within a specified time for certain levels of
demand. P2/5 is fundamentally a
probabilistic approach but the application of it is generally required to
be done deterministically.
P2/6 was essentially a revision
of P2/5 in July 2006 to recognise the increasing role that distributed
generation could play in securing supply as historic smaller (eg. 120 MW
unit) coal stations were retired. The requirements for demand security
were unchanged in P2/6. P2/6 overlaps the National Electricity
Transmission System Security & Quality of Supply Standards (NETS SQSS)
which is the equivalent planning and operation standards used by transmission
licensees.
Philosophical difficulties with the current P2/6 and SQSS
The
following philosophical difficulties have been identified…
· How useful is it to still be using an engineering standard such
as P2/6 that reflects 1970’s practices and technologies.
· Although P2/6 and SQSS have a common origin, differences in
specific terminology and interpretation have led to difficulties in confirming
transmission license compliance and Grid Supply Points.
Specific shortcomings of P2/6
A few
specific shortcomings of P2/6 include…
· The underlying value of kWh not supplied reflects 1970’s
levels, and also does not reflect other factors such as how different classes
of customers value a kWh not supplied, and how the value of a kWh not supplied
varies with outage duration.
· Failure rates, restoration times and repair times have
varied a lot since the 1970’s.
· An increase in the amount of data on the security of supply
provided by distributed generation since P2/6 was written.
· It doesn’t recognise how the various incentive mechanisms or
the RIIO framework incentivise network design.
All
these issues are getting folded into the review process, and Pipes & Wires
will comment further as that review progresses. Thanks to Mike Kay of P2
Analysis Ltd for contributing to this article.
Global - withdrawal of asset management standard PAS 55:2008
Readers
should note that the asset management standard PAS 55:2008 was withdrawn on 1st
February 2015, and effectively superseded by ISO 55000. That doesn’t mean that
all the hard work of achieving PAS 55 certification is now worthless, but
rather that the internationally consistent ISO 55000 is now the preferred
standard. To discuss how your company can move towards ISO 55000 certification,
pick here.
Cool stuff
Newly published book – “Keeping The Lights On”
Well-known
electricity historian and author Helen Reilly has recently published her latest
book “Keeping The Lights On – The History Of System Operations In New Zealand
1939 – 2013”. Pick here to order your copy for only $46.50 from Grid Heritage. It’s
a thoroughly good read, and complements Helen’s previous book “Connecting The
Country”.
Recent client projects
Here’s
a sample of work done for clients over the last few years that demonstrate the
breadth of skills, insight and experience that is available from Utility
Consultants....
· Advising a major global investment bank on the revenue and
capital cost characteristics of the New Zealand generation industry.
· Assessing the investment characteristics of proposed CapEx
increases to an investor-owned electric network.
· Assessing three EDB’s asset management practices against ISO
55000:2014.
· Assessing an EDB’s compliance with the lines – generation
separation requirements of the Electricity Industry Act 2010.
· Assessing an EDB’s compliance with the Electricity Industry
Participation Code.
· Compiling safe operating procedures for a wide range of
distribution switches.
· Advising an investor on the investment characteristics and
regulatory constraints of small hydro development and grid connection.
· Reviewing the engineering aspects of an EDB’s lines pricing
methodology.
· Advising a major global consultancy on specific features of
emerging electricity transmission and distribution regulatory regimes,
including period length, potential for re-opening determinations, caps &
collars, total expenditure levels and incentive mechanisms.
· Examining the economic efficiencies of an EDB’s pricing
methodologies.
· Advised on the wider philosophical and potential tax issues
of the way consumer discounts are paid by EDB’s.
· Prepared an independent engineer’s report to justify
proposed alternative asset lives.
· Advised an electricity business on the regulatory
implications of bringing externally contracted field services back in-house.
· Identified economic and regulatory arguments to support
inclusion of transmission interconnection charge risk into network tariffs.
· Advised lines businesses on a regulator’s proposed treatment
of CapEx and OpEx.
· Advised an international investor on gas distribution policy
and regulatory trends.
· Identified national energy policy implications for lines
businesses.
· Assisted a lines business to identify the burden of proof
implied by regulatory determinations.
· Suggested amendments to a gas transmission AMP to strengthen
the economic arguments.
· Identified electricity network investment characteristics as
part of an acquisition study.
· Developed an AM framework for a gas distribution business to
link AM to regulatory requirements.
· Identified OpEx – CapEx tradeoffs for an electricity lines business.
· Performed various substation growth and reinforcement
assessments.
· Performed network physical and business risk studies.
· Compiled disaster recovery and business continuity plans.
Pick here to download a profile of recent projects, or here to contact Phil.
General stuff
Guide to NZ electricity laws
I’ve
compiled a “wall chart” setting out the relationship between various past and
present electricity Acts, Regulations, Codes etc in sort of a chronological
progression. To request your free copy, pick here. It looks really cool printed in color as an A2 or A1 size.
A bit of light-hearted humor
What
if price control had been around in the 1920’s and 1930’s ? A collection of
photo’s with humorous captions looks at some of the salient features of price
control. Pick here to download.
Conferences & training courses
The
following conferences and training courses are planned...
· Fundamentals of the NZ electricity industry, 7th – 8th September 2015,
Wellington.
· Fundamentals of the NZ electricity industry, 19th – 20th October 2015,
Auckland.
Utility
Consultants takes no responsibility for the content of individual courses or
conferences, nor for any administrative or travel arrangements.
Wanted – old electricity history books
If
anyone has an old copy of the following books (or any similar books) they no
longer want I’d be happy to give them a good home…
· Economic Operation Of Power Systems (Kirchmayer).
· Distribution Of Electricity (WT Henley, the cable
manufacturer)
· Northwards March The Pylons.
· Two Per Mile.
· Live Lines (the old ESAA journal).
· The Engineering History Of Electric Supply In New Zealand.
Opt out from Pipes & Wires
Pick
this link to opt out from Pipes & Wires. Please ensure that you
send from the email address we send Pipes & Wires to.
Disclaimer
These articles are
of a general nature and are not intended as specific legal, consulting or
investment advice, and are correct at the time of writing. In particular Pipes
& Wires may make forward looking or speculative statements, projections or
estimates of such matters as industry structural changes, merger outcomes or
regulatory determinations. These articles also summarise lengthy documents, and it is important that readers refer to those
documents in forming opinions or taking action.
Utility
Consultants Ltd accepts no liability for action or inaction based on the
contents of Pipes & Wires including any loss, damage or exposure to
offensive material from linking to any websites contained herein, or from any
republishing by a third-party whether authorised or not, nor from any comments posted on Linked In, Face Book or similar
by other parties.