Pipes & Wires

INSIGHT AND ANALYSIS OF TOPICAL ENERGY & INFRASTRUCTURE ISSUES

Issue 138 – October 2014

 

From the editor’s desk…

 

Welcome to Pipes & Wires #138. This issue covers the following matters…

 

·       Energy storage in the United States.

 

·       A couple of regulatory decisions in New Zealand.

 

·       Generation policy and planning in Germany.

 

·       Gas market consolidation in France.

 

·       Proposed electricity privatisation in Australia.

 

So … until next month, happy reading…

 

Matters for attention in NZ

 

Readers’ attention is drawn to the following matters…

 

·     Revised standard NZS7901:2014 for Safety Management Systems.

 

·     Increased obligations for worker safety.

 

·     The Electricity Authority’s intention to “improve distribution efficiency”.

 

Cool video clips

 

This 6 minute video clip shows the remote controlled gas turbine generator built by the South-Western Electricity Board (now part of Western Power Distribution) in England in 1959. The technology is fascinating.

 

North America

 

US – storing wind energy

 

Introduction

 

The intermittent nature of wind energy is becoming an increasing problem in many countries. This article examines the planned Pathfinder Wind Energy project which includes a compressed air energy storage (CAES) project to store wind-generated electricity until it is needed.

 

Key features of the project

 

The key features of the overall project include…

 

·     A 2,100MW wind farm spread over 600km2 of Platte County, Wyoming.

 

·     The Zephyr Power Transmission Project, A 500kV HVDC line stretching about 1,370km from Chugwater, Wyoming to the Eldorado Valley, Nevada, from where existing lines can transmit the electricity to Los Angeles and then to the remainder of California.

 

·     A 1,200MW compressed air energy storage facility part way along the Zephyr HVDC line to store the energy until it is needed by California. The CAES would be based on 4 underground vertical salt caverns near Delta, Utah each about 400m high and 90m in diameter and capable of storing a total of 60,000 MWh of electricity.

 

The partners to the project

 

The partners to the project include…

 

·     Duke American Transmission, a joint venture between Duke Energy and American Transmission Co.

 

·     Pathfinder, which includes Magnum Energy and Dresser-Rand.

 

The costs and benefits of Pathfinder

 

All this doesn’t come cheap … the final cost is expected to be about $8b. So what about the benefits ? They include…

 

·     Capturing low cost wind energy that could save California electricity customers about $600m per year.

 

·     Exploiting the negative correlation of wind speeds between California and Wyoming.

 

Sounds like an awesome project … the engineering alone seems fascinating !!!

 

US – mandating regionally coordinated transmission grid planning

 

Introduction

 

Regionally coordinated transmission grid planning sounds like a good idea … the whole idea of minimsing total economic cost of building new transmission lines has a good sound to it. This brief article examines the Federal Energy Regulatory Commission’s (FERC) recently released Order 1000.

 

Regulatory framework

 

The background regulatory framework is the Federal Power Act of 1935 which broadly gives the federal government jurisdictional authority over “interstate electricity transmission and wholesale power sales”.

 

Key features of Order 1000

 

The FERC introduced Order 1000 in July 2011 which broadly requires public utility transmission providers (but excludes FERC-approved ISO’s or RTO’s) to…

 

·     Enroll in a regional transmission planning process.

 

·     Include a regional cost allocation method for projects in the resulting regional transmission plan.

 

Enrolment for non-public utility transmission providers is optional, however if they do enroll they are subject to the regional cost allocation method.

 

Order 1000 was clarified and affirmed by Orders 1000-A and 1000-B, and then further affirmed in August 2014 by the US Court of Appeals for Washington DC.

 

Implications for public utility transmission providers

 

So it appears that any electric company with interstate transmission lines that is not already part of a FERC-approved ISO or RTO will need enroll in a regional transmission planning process (which might end up looking like the former Australian VENCorp or ESIPC agencies).

 

The 2nd step of constructing a regional cost allocation method is likely to prove challenging, as there are always winners and losers amongst connected grid users.

 

US – challenging feed-in tariffs in a competitive supply arrangement

 

Introduction

 

The saga of nett metering and feed-in tariffs continues. This article examines a challenge to the nett metering law in the US state of Ohio.

 

The key issue

 

The key issue is that whilst electric customers can choose their energy suppliers (and in Ohio, it appears that 30% pf domestic customers and 80% of industrial customers have), the feed-in tariff must be paid by the incumbent electric company. Moreover, the cost of that feed-in tariff often cannot be adequately recovered by the incumbent through its regulated tariffs.

 

The legal challenge

 

Challenges to the Ohio statute have been bought by both AEP Ohio and First Energy Corporation, who claim that the competitive suppliers should have to pay the feed-in tariffs, not the incumbent ie. the competitive supplier can capture the benefits but not the costs. To be clear, AEP Ohio and First Energy have clearly stated that they do not oppose nett metering.

 

For its part, the Public Utilities Commission of Ohio (PUC) is arguing that the matter does not fall into the Ohio Supreme Court’s jurisdiction. So … it will be interesting to see where this goes, and whether the authorities will recognise that new entrants must pick up their share of the costs.

 

New Zealand

 

NZ – the draft electricity default price-quality path

 

Introduction

 

On 20th October 2014 the Commerce Commission released a draft default price-quality path (DPP) that is intended to apply to all non-exempt electricity distribution businesses (EDB’s) for the regulatory period 1st April 2015 to 31st March 2020.

 

Regulatory framework

 

The regulatory framework is Part 4 of the Commerce Act 1986, in particular the following …

 

·     Section 52D – meaning and application of claw-back.

 

·     Subpart 3 – input methodologies.

 

·     Subpart 6 – default / customised price-quality regulation.

 

·     Subpart 9 – electricity line services.

 

Key features of the draft DPP

 

Key features of the draft DPP include…

 

·     Specifying the time windows during a customised price-path (CPP) proposal can be submitted.

 

·     Specifying the maximum allowable revenue (MAR) for each EDB.

 

·     Specifying the annual rate of change in MAR.

 

·     Specifying how the notional revenue is to be calculated.

 

·     Specifying how pass-through costs must be calculated.

 

·     Specifying how any changes in pricing methodology or amalgamation of customer groups must be treated.

 

·     Requiring the Commission to be notified of a Major Transaction.

 

·     Specifying the contents of an annual compliance statement

 

The Commission expects to release the final DPP by the end of November 2014.

 

NZ – setting the WACC for electricity distribution

 

Introduction

 

The Commerce Commission has recently determined the cost of capital that will apply to any customised price path (CPP) application made by an electricity distribution businesses after 30th September 2014. This article examines the key features of that determination.

 

Legal frameworks

 

This WACC has been compiled pursuant to Clauses 5.3.22 to 5.3.29 of the Electricity Distribution Services Input Methodologies Determination 2012, which is made pursuant to Part 4 of the Commerce Act 1986.

 

Key features of the determination

 

The Commission has determined the following WACC parameters…

 

Parameter

3 year estimate

4 year estimate

5 year estimate

Risk-free rate

3.91%

4.00%

4.09%

Debt premium

1.45%

1.55%

1.65%

Equity beta

0.61

0.61

0.61

Debt issuance costs

0.58%

0.44%

0.35%

Leverage

44%

44%

44%

Cost of debt

5.94%

5.99%

6.09%

Cost of equity

7.09%

7.15%

7.21%

Midpoint vanilla WACC

6.58%

6.64%

6.72%

 

Previous WACC decisions

 

Some of the Commissions’ previous WACC decisions are as follows.

 

WACC decision applies to

Approx date

Mid-point WACC

75th percentile WACC

All electricity CPP applications after 30/9/14

September 2014

Vanilla 6.58%, 6.64%, 6.72%

 

Auckland, Christchurch Airports for 2015 disclosure year

July 2014

Vanilla 7.64%

Vanilla 8.63%

Vector, GasNet for 2015 disclosure year

July 2014

Vanilla 7.54%

Vanilla 8.35%

Transpower for 2015 disclosure year

July 2014

Vanilla 6.83%

Vanilla 7.55%

Wellington Airport for 2015 disclosure year

April 2014

Vanilla 7.70%

 

EDB’s for 2015 disclosure year

April 2014

Vanilla 6.89%

 

Powerco gas CPP applications before 3/15

March 2014

Vanilla 5-year 7.54%

Vanilla 5-year 8.35%

Maui pipeline (gas transmission)

January 2014

Vanilla 7.64%, post-tax 6.85%

 

Vector, GasNet CPP applications before 12/14

December 2013

Vanilla 7.56%

 

All CPP applications before 30/9/14

September 2013

Vanilla from 6.26% to 6.69%

Vanilla from 6.97% to 7.41%

Transpower

July 2013

 

Vanilla 6.85% , post-tax 6.17%

Vector gas distribution, GasNet

July 2013

 

Vanilla 7.65%, post-tax 6.97%

Auckland & Christchurch airports

July 2013

 

Vanilla 8.00%, post-tax 7.75%

All electricity distribution

April 2013

 

Vanilla 6.83%, post-tax 6.14%

Maui pipeline (gas transmission)

February 2013

 

Vanilla 7.46%, post-tax 6.80%

All gas distribution and gas transmission DPP’s

December 2012

 

Vanilla 6.63%

Vector, GasNet CPP’s

December 2012

Vanilla 6.39% (5 years)

 

Powerco gas distribution

October 2012

Vanilla 6.83%, post-tax 6.12%

 

 

NZ – amending the electricity distribution services Input Methodology

 

Introduction

 

Pipes & Wires #135 examined the Commerce Commission’s consultation paper on proposed amendments to the Input Methodologies (IM) for electricity distribution services. This article examines the Commission’s Determination Amendment that was published in late September 2014.

 

Legal framework for the IM

 

The legal framework for the IM’s is Subpart 3 of Part 4 of the Commerce Act 1986. This subpart inter alia sets out the purpose of the IM’s, what issues they must address, and the process for establishing and amending IM’s.

 

Principal amendment to the IM

 

The principal amendment is the insertion of a new clause 4.4.10 which amends the reference to “6 months” in clauses 4.4.1(1)(c), 4.4.3(c), 4.4.4(2)(b), 4.4.5(1)(a), 4.4.6(a) and 4.4.7(1)(b) to “5 months”.

 

NZ – amending the Transpower Input Methodology

 

Introduction

 

Pipes & Wires #134 examined the Commerce Commissions’ consultation paper proposing amendments to two of the Input Methodologies (IM’s) that apply to Transpower. This article examines the Commission’s Determination Amendment that was published in late September 2014

 

Legal framework

 

Transpower’s regulatory framework is established by Part 4 of the Commerce Act 1986, viz…

 

·     Subpart 3, which defines inter alia the purpose of IM’s, the matters that must be addressed by the IM’s, and the process that the Commission must follow in determining the IM’s.

 

·     Subpart 7, which provides for an Individual Price-Quality Path to be applied as the Commission sees fit subject to correctly applying all applicable IM’s.

 

·     Subpart 9, which inter alia subjects all electricity distribution businesses to information disclosure.

 

The IM’s that the Commission proposes to amend

 

The Commission proposes to amend the following two IM’s…

 

·     Transpower Input Methodologies Determination 2012 (NZCC 17).

 

·     Transpower Capital Expenditure Input Methodology Determination 2012 (NZCC 2).

 

Principal amendment to IM (NZCC #17)

 

Similar to the principal amendment to the Electricity Distribution Services IM, the principal amendment to NZCC #17 is the insertion of a new clause 3.5.11 which amends the reference to “6 months” in clauses 3.5.1(1)(c), 3.5.3(c), 3.5.4(2)(b), 3.5.5(1)(a), 3.5.6(a) and 3.5.7(1)(b) to “5 months”.

 

UK & Europe

 

Germany – closing generation capacity

 

Introduction

 

We’ve seen clearly how Germany’s Erneuerbare Energien Gesetz (Renewable Energy Sources Act) is prioritising renewable generation, with the unsurprising consequence of fossil and nuclear generation being increasingly relegated to peaking plant that struggles to earn its keep in a market that pays for generated kWh. This article examines the requirement for generation plant closures to be approved by the Bundesnetzagentur (the Federal Energy Regulator).

 

Regulatory framework

 

The regulatory framework for seeking approval to close generation capacity is set out in s13a of the Gesetz uber die Elektrizitats und Gasversorgung (Law on Electricity & Gas Supply). This requires generation owners to seek the approval of the Bund to close generation capacity.

 

Generation closures

 

Over the last few years Germany has been closing coal and nuclear generation, so let’s try to wrap some numbers around this to gain a sense of how pressing this issue might really be. Germany has about 170,000MW of installed generation capacity … that’s a convenient enough baseline figure to keep in mind.

 

The figure that probably grabs the most exposure is the planned shutdown of the nuclear stations by 2022, which amounts to about 12,000MW. As of September 2014 the Bund has applications for closure for about 7,740MW of capacity. So that is somewhere around about 18,000MW of generation to be closed over the next 8 years or so. If we now consider that Germany has about 70,000MW of wind and solar and then apply a capacity factor of say 0.5 we could conclude that only about 35,000MW of that wind and solar capacity is firm (maybe I’m being generous here).

 

Working downwards from the baseline of 170,000MW, we end up with something like 120,000MW of firm capacity by 2022, which seems a bit scary.

 

The Bund can refuse closure

 

The Bund can refuse to allow closure if generation is deemed critical to grid stability, and indeed 7 units (all in southern Germany) have been deemed critical. Hence the owners will be refused approval to close them, and will be paid compensation to keep them running.

 

Possible implications

 

The number of grid stability emergencies in Germany has increased significantly over the last few years due to both the increasing presence of renewables and the Erneuerbare Energien Gesetz requirement to prioritise the dispatch of those renewables. Moreover, the big 4 generators (E.On, RWE, Vattenfall and EnBW) seem reluctant to continue to maintain coal-fired generation that is being increasingly shut out of the market.

 

So it would seem that Germany’s electricity supply system is going to face continued doubtful security, and possibly a further layer of costs to keep thermal plant on stand-by.

 

France – consolidating the gas markets

 

Introduction

 

Over the years Pipes & Wires has briefly examined both the consolidation of France’s high pressure gas transmission markets and the features of the ATRT5 tariff. This article examines the Commission de Régulation de l’Énergie’s (CRE) recent deliberation to establish a single market place.

 

The key issues

 

The 3 high pressure gas balancing zones that were introduced on 1st January 2009 led to the following difficulties…

 

·     Access to the south of France remains difficult, with no access for the Fos-sur-Mer LNG terminal.

 

·     The desire to interconnect with the Spanish gas transmission system.

 

·     The need to strengthen gas import capacity from North Africa.

 

The Gascogne-Midi project

 

The Gascogne-Midi project will comprise €171m of investment as follows…

 

·     TGIF will build a new compressor station at Barbaira, and a new segment of pipeline.

 

·     GRTgaz will modify the Cruzy gas station, and change the direction of gas flow at Saint Martin de Crau.

 

The key benefits will be improved transmission capacity from Spain to France, which will be important if Europe increases it LNG importation.

 

Tariff amendments

 

At the time of writing, the CRE is expecting to allow the 3% WACC premium embodied in the ATRT5 tariff framework to incentivise this investment.

 

Australia

 

Queensland – privatising the electricity networks

 

Introduction

 

Privatising electricity assets seems to be always close at hand as Australia’s state governments come under increasing pressure to both improve efficiency and release funding for health and transport. This article examines the Queensland government’s recent proposal to offer long-term leases of the transmission grid and the 2 distribution networks.

 

The assets involved

 

The 3 following electricity assets are involved…

 

·     Electricity transmission grid owner PowerLink.

 

·     Electricity distribution network owner Energex (south-east Queensland).

 

·     Electricity distribution network owner Ergon Energy (remainder of the state).

 

The proposed lease arrangements

 

The state governments’ plan is to offer long-term leases of the 3 assets, possibly for either 50 years with an option for a further 49 years, or simply for 99 years (some might recall that this seems similar to the 200 year lease arrangement that SA Power Networks operates under).

 

There are 2 main reasons why a lease arrangement might be considered…

 

·     Outright sale is simply too hard politically, noting that Queensland has a very vigorous trade union movement.

 

·     Sometimes legislation prohibits the outright sale of the assets (as it does in South Australia).

 

The opposition

 

Not surprisingly, opposition has come from the trade unions, who have raised the following concerns…

 

·     Jobs will be lost.

 

·     Supply reliability and public safety will inevitably suffer.

 

·     Electricity prices will rise, especially in rural areas.

 

In regard to the last 2 items, the experience in Victoria at least is quite the opposite … supply reliability has been maintained and electric lines charges have declined.

 

Next steps

 

The state elections must be held by 20th June 2015, and it is expected that the election will be a referendum on leasing state assets. The Liberal-National Party has already unanimously supported the lease plan, and hence a win at the polls for the LNP will mean that the leasing process will proceed.

 

Recent client projects

 

Here’s a sample of work done for clients over the last few years that demonstrate the breadth of skills, insight and experience that is available from Utility Consultants....

 

·     Advising a major global investment bank on the revenue and capital cost characteristics of the New Zealand generation industry.

 

·     Assessing the investment characteristics of proposed CapEx increases to an investor-owned electric network.

 

·     Assessing two EDB’s asset management practices against ISO 55000:2014.

 

·     Assessing an EDB’s compliance with the lines – generation separation requirements of the Electricity Industry Act 2010.

 

·     Assessing an EDB’s compliance with the Electricity Industry Participation Code.

 

·     Compiling safe operating procedures for a wide range of distribution switches.

 

·     Advising an investor on the investment characteristics and regulatory constraints of small hydro development and grid connection.

 

·     Reviewing the engineering aspects of an EDB’s lines pricing methodology.

 

·     Advising a major global consultancy on specific features of emerging electricity transmission and distribution regulatory regimes, including period length, potential for re-opening determinations, caps & collars, total expenditure levels and incentive mechanisms.

 

·     Examining the economic efficiencies of an EDB’s pricing methodologies.

 

·     Advised on the wider philosophical and potential tax issues of the way consumer discounts are paid by EDB’s.

 

·     Prepared an independent engineer’s report to justify proposed alternative asset lives.

 

·     Advised an electricity business on the regulatory implications of bringing externally contracted field services back in-house.

 

·     Identified economic and regulatory arguments to support inclusion of transmission interconnection charge risk into network tariffs.

 

·     Advised lines businesses on a regulator’s proposed treatment of CapEx and OpEx.

 

·     Advised an international investor on gas distribution policy and regulatory trends.

 

·     Identified national energy policy implications for lines businesses.

 

·     Assisted a lines business to identify the burden of proof implied by regulatory determinations.

 

·     Suggested amendments to a gas transmission AMP to strengthen the economic arguments.

 

·     Identified electricity network investment characteristics as part of an acquisition study.

 

·     Developed an AM framework for a gas distribution business to link AM to regulatory requirements.

 

·     Identified OpEx CapEx tradeoffs for an electricity lines business.

 

·     Performed various substation growth and reinforcement assessments.

 

·     Performed network physical and business risk studies.

 

·     Compiled disaster recovery and business continuity plans.

 

Pick here to download a profile of recent projects, or here to contact Phil.

 

General stuff

 

Guide to NZ electricity laws

 

I’ve compiled a “wall chart” setting out the relationship between various past and present electricity Acts, Regulations, Codes etc in sort of a chronological progression. To request your free copy, pick here. It looks really cool printed in color as an A2 or A1 size.

 

Recently released book “Small Hydroelectric Engineering Practice”

 

Well-known hydroelectric engineer Bryan Leyland has recently published a book entitled “Small Hydroelectric Engineering Practice”. This is a comprehensive reference book covering all aspects of identifying, building and operating hydroelectric schemes between 500kW and 50MW. Pick here for more details.

 

A bit of light-hearted humor

 

What if price control had been around in the 1920’s and 1930’s ? A collection of photo’s with humorous captions looks at some of the salient features of price control. Pick here to download.

 

Conferences & training courses

 

The following conferences and training courses are planned...

 

·     21st Africa Oil Week, Cape Town, 3rd – 7th November 2014.

 

·     Fundamentals of the NZ electricity industry, Wellington, 16th – 17th March 2015.

 

·     Fundamentals of the NZ electricity industry, Auckland, 20th – 21st April 2015.

 

Utility Consultants takes no responsibility for the content of individual courses or conferences, nor for any administrative or travel arrangements.

 

Wanted – old electricity history books

 

If anyone has an old copy of the following books (or any similar books) they no longer want I’d be happy to give them a good home…

 

·     Distribution Of Electricity (WT Henley, the cable manufacturer)

 

·     Northwards March The Pylons.

 

·     Two Per Mile.

 

·     Live Lines (the old ESAA journal).

 

·     The Engineering History Of Electric Supply In New Zealand.

 

House-keeping stuff

 

Opt out from Pipes & Wires

 

Pick this link to opt out from Pipes & Wires. Please ensure that you send from the email address we send Pipes & Wires to.

 

Disclaimer

 

These articles are of a general nature and are not intended as specific legal, consulting or investment advice, and are correct at the time of writing. In particular Pipes & Wires may make forward looking or speculative statements, projections or estimates of such matters as industry structural changes, merger outcomes or regulatory determinations. These articles also summarise lengthy documents, and it is important that readers refer to those documents in forming opinions or taking action.

 

Utility Consultants Ltd accepts no liability for action or inaction based on the contents of Pipes & Wires including any loss, damage or exposure to offensive material from linking to any websites contained herein, or from any republishing by a third-party whether authorised or not, nor from any comments posted on Linked In, Face Book or similar by other parties.