Pipes & Wires

INSIGHT AND ANALYSIS OF TOPICAL ENERGY & INFRASTRUCTURE ISSUES

Issue 136 – August 2014

 

From the editor’s desk…

 

Welcome to Pipes & Wires #136 … this month we start with 2 cost of capital determinations in NZ before examining the emerging ISO 37120 standard and what it might mean for electric companies. We then examine a regulatory decision and 2 mergers in the US, followed by a draft regulatory determination in the UK. This issue concludes with an examination of solar tariffs in Australia and a discussion of those tariffs need to reconcile with distribution pricing.

 

Recent client projects

 

Here’s a sample of work done for clients over the last few years that demonstrate the breadth of skills, insight and experience that is available from Utility Consultants....

 

·     Advising a major global investment bank on the revenue and capital cost characteristics of the New Zealand generation industry.

 

·     Assessing the investment characteristics of an investor-owned electric network.

 

·     Assessing a large EDB’s asset management practices against ISO 55000:2014.

 

·     Assessing an EDB’s compliance with the lines – generation separation requirements of the Electricity Industry Act 2010.

 

·     Compiling safe operating procedures for a wide range of distribution switches.

 

·     Advising an investor on the investment characteristics and regulatory constraints of small hydro development and grid connection.

 

·     Reviewing the engineering aspects of an EDB’s lines pricing methodology.

 

·     Advising a major global consultancy on specific features of emerging electricity transmission and distribution regulatory regimes, including period length, potential for re-opening determinations, caps & collars, total expenditure levels and incentive mechanisms.

 

·     Examining the economic efficiencies of an EDB’s pricing methodologies.

 

·     Advised on the wider philosophical and potential tax issues of the way consumer discounts are paid by EDB’s.

 

·     Prepared an independent engineer’s report to justify proposed alternative asset lives.

 

·     Advised an electricity business on the regulatory implications of bringing externally contracted field services back in-house.

 

·     Identified economic and regulatory arguments to support inclusion of transmission interconnection charge risk into network tariffs.

 

·     Advised lines businesses on a regulator’s proposed treatment of CapEx and OpEx.

 

·     Advised an international investor on gas distribution policy and regulatory trends.

 

·     Identified national energy policy implications for lines businesses.

 

·     Assisted a lines business to identify the burden of proof implied by regulatory determinations.

 

·     Suggested amendments to a gas transmission AMP to strengthen the economic arguments.

 

·     Identified electricity network investment characteristics as part of an acquisition study.

 

·     Developed an AM framework for a gas distribution business to link AM to regulatory requirements.

 

·     Identified OpEx CapEx tradeoffs for an electricity lines business.

 

·     Performed various substation growth and reinforcement assessments.

 

·     Performed network physical and business risk studies.

 

·     Compiled disaster recovery and business continuity plans.

 

Pick here to download a profile of recent projects, or here to contact Phil.

 

Matters for attention in NZ

 

Readers’ attention is drawn to the following matters…

 

·     Revised standard NZS7901:2014 for Safety Management Systems.

 

·     Likely increased obligations for worker safety.

 

New Zealand

 

NZ – determining the WACC for electric, gas and airports

 

Introduction

 

The Commerce Commission has recently determined the cost of capital (Vanilla WACC) that will apply to the following infrastructure businesses for the information disclosure year ending on 30th June 2015...

 

·     Transpower.

 

·     Vector and GasNet’s gas pipeline businesses.

 

·     Auckland and Christchurch Airports’ specified airport services.

 

This article examines the key features of that determination.

 

Legal frameworks

 

These WACC’s have been compiled pursuant to…

 

·     Clauses 2.4.1 to 2.4.7 of the Commerce Act (Transpower Input Methodologies) Determination 2012.

 

·     Clauses 2.4.1 to 2.4.7 of the Commerce Act (Gas Distribution Services Input Methodologies) Determination 2012.

 

·     Clauses 2.4.1 to 2.4.7 of the Commerce Act (Gas Transmission Services Input Methodologies) Determination 2012.

 

·     Clauses 5.1 to 5.7 of the Commerce Act (Specified Airport Services Input Methodologies) Determination 2010.

 

These determinations themselves are made pursuant to Part 4 of the Commerce Act 1986.

 

Key features of the determination

 

The Commission has determined the following WACC parameters…

 

Parameter

Transpower

Vector & GasNet

Auckland & Christchurch Airports

Risk-free rate (5 years)

4.17%

4.17%

4.17%

Debt premium (5 years)

1.75%

1.75%

1.18%

Equity beta

0.61

0.79

0.72

Debt issuance costs (5 years)

0.35%

0.35%

0.35%

Leverage

44%

44%

17%

Pre-tax cost of debt (5 year)

6.27%

6.27%

5.70%

Cost of equity (5 years)

7.27%

8.53%

8.04%

75th percentile vanilla WACC

7.55%

8.35%

8.63%

75th percentile post-tax WACC

6.78%

7.57%

8.36%

25th percentile vanilla WACC

6.11%

6.73%

6.66%

25th percentile post-tax WACC

5.34%

5.95%

6.39%

Midpoint vanilla WACC

6.83%

7.54%

7.64%

Midpoint post-tax WACC

6.06%

6.76%

7.37%

 

Previous WACC decisions

 

Some of the Commissions’ previous WACC decisions are as follows.

 

WACC decision applies to

Approx date

Mid-point WACC

75th percentile WACC

Auckland, Christchurch Airports for 2015 disclosure year

July 2014

Vanilla 7.64%

Vanilla 8.63%

Vector, GasNet for 2015 disclosure year

July 2014

Vanilla 7.54%

Vanilla 8.35%

Transpower for 2015 disclosure year

July 2014

Vanilla 6.83%

Vanilla 7.55%

Wellington Airport for 2015 disclosure year

April 2014

Vanilla 7.70%

 

EDB’s for 2015 disclosure year

April 2014

Vanilla 6.89%

 

Powerco gas CPP applications before 3/15

March 2014

Vanilla 5-year 7.54%

Vanilla 5-year 8.35%

Maui pipeline (gas transmission)

January 2014

Vanilla 7.64%, post-tax 6.85%

 

Vector, GasNet CPP applications before 12/14

December 2013

Vanilla 7.56%

 

All CPP applications before 30/9/14

September 2013

Vanilla from 6.26% to 6.69%

Vanilla from 6.97% to 7.41%

Transpower

July 2013

 

Vanilla 6.85% , post-tax 6.17%

Vector gas distribution, GasNet

July 2013

 

Vanilla 7.65%, post-tax 6.97%

Auckland & Christchurch airports

July 2013

 

Vanilla 8.00%, post-tax 7.75%

All electricity distribution

April 2013

 

Vanilla 6.83%, post-tax 6.14%

Maui pipeline (gas transmission)

February 2013

 

Vanilla 7.46%, post-tax 6.80%

All gas distribution and gas transmission DPP’s

December 2012

 

Vanilla 6.63%

Vector, GasNet CPP’s

December 2012

Vanilla 6.39% (5 years)

 

Powerco gas distribution

October 2012

Vanilla 6.83%, post-tax 6.12%

 

 

NZ – proposed change to the WACC determination date

 

Introduction

 

The Commerce Commission recently released a consultation paper proposing to amend the Input Methodologies (IM) that set the date that the WACC is determined for electricity distribution Default Price Paths (DPP’s) and for Transpower’s Individual Price Path (IPP). This is a continuation of the Commission’s work on determining the most appropriate WACC percentile.

 

Legal framework

 

The legal framework for the amendments consists of the…

 

·     Electricity Distribution Services Input Methodologies Determination 2012 (“NZCC 26”).

 

·     Transpower Input Methodologies Determination 2012 (“NZCC 17”).

 

Both of these IM’s are made pursuant to Subpart 3 of Part 4 of the Commerce Act 1986.

 

Proposed amendments

 

The Commission proposes to amend the date by which it must determine the WACC for electricity DPP’s and for Transpower IPP’s from 30th September to 31st October. The following detailed amendments are proposed…

 

·     Various sub-clauses of clause 4.4 of the electricity distribution IM are amended to read 5 months, not 6.

 

·     Various sub-clauses of clause 3.5 of the Transpower IM are amended to read 5 months, not 6.

 

Next steps

 

The Commission has consulted on this issue and expects to reach its Final Decision in this matter by 30th September 2014 and a Final Decision on the WACC percentile by 31st October 2014.

 

Global

 

Global – possible impact of the ISO 37120 standard

 

Introduction

 

Over the years Pipes & Wires has observed that many local governments are placing increasing expectations and obligations on electric companies (whether local government owned or not) to contribute to sustainable development of communities. This article briefly notes the development of ISO 37120:2014 which provides indicators for city services and quality of life, and considers how that standard might impact on electric company operations.

 

How ISO 37120 might effect electric companies

 

ISO 37120 covers 17 aspects of urban development. Energy is obviously 1 aspect that will effect electric companies, however it is possible that other aspects will also effect electric companies…

 

·     Economy – electric reliability in support of economic growth.

 

·     Environment – planning of large structures such as generation plants, transmission lines and substations.

 

·     Finance – dividends paid to the city by a Muni.

 

·     Fire & emergency response – ability to restore electric supply after a disaster or civil emergency.

 

·     Safety – safety of electrical equipment.

 

·     Wastewater – sustainability of electricity used for processing and pumping.

 

·     Water supply – sustainability of electricity used for processing and pumping.

 

The specific indicators around energy

 

The energy indicator has 7 sub-indicators as follows…

 

Core indicators

7.1

Total residential electrical energy used per capita (kWh/year).

7.2

Percentage of city population with authorized electrical service.

7.3

Energy consumption of public buildings per year (kWh/m2).

7.4

Percentage of total energy consumed derived from renewable sources

Supporting indicator

7.5

Total electrical energy use per capita (kWh/year).

7.6

Average number of electrical interruptions per customer per year

7.7

Average length of electrical interruptions.

 

Electric companies might prima facie be held responsible for sub-indicators 7.4, 7.6 and 7.7, however it is always possible that the world of local government might simply expect electric companies to influence and be responsible for all 7 sub-indicators (and quite likely without being paid for it).

 

Possible responses by electric companies

 

Electric companies might consider the following pre-emptive responses…

 

·     Ensuring that investor-owned electric companies are fairly compensated for costs or lost revenue resulting from any changes in urban policy eg. increased undergrounding of lines and substations.

 

·     Ensuring that Muni’s inform their owners of the likely impact on future dividends if they are required to create public policy outcomes.

 

·     Ensuring that local governments are fully informed of the costs and security of supply implications of increased renewable generation.

 

·     Ensuring that urban policy doesn’t impact on supply reliability or restoration eg. requiring an arborist to be present before cable repairs can commence, or allowing fault trucks to drive in emergency lanes.

 

·     Assisting local government to understand public building energy efficiency issues, and the likely costs.

 

·     Ensuring that local government understand that electric companies must recover the costs of new reticulation assets (sub-indicator 7.2).

 

North America

 

US – regulating the “build or buy” decision

 

Introduction

 

Excessive capacity in any market has the potential to depress prices, dilute returns and potentially threaten genuine long-term investment. This article examines a request for a state regulator to intervene in a “build or buy” decision on the side of “buying” existing generation capacity.

 

The factual position

 

Duke Energy Florida has sought approval from the Florida Public Service Commission (PSC) to build 2,200MW of new gas fired generation by 2018, including a new 1,640MW station and 560 MW of peaking generation at the existing Crystal River site. This proposed new capacity will meet expected load growth and off-set the closure of the 860MW #3 nuclear unit and 2 of the 4 coal-fired units, all at Crystal River.

 

In accordance with state law, Duke called for tenders for the construction of the new plants. Duke itself also tendered for the work, and was the successful tenderer.

 

The request for intervention

 

As part of Duke’s approval to build the new generation capacity, the following companies have intervened in Duke’s application…

 

·     Calpine Construction Finance.

 

·     NRG Florida.

 

·     EFS Shady Hills.

 

All 3 of these parties own generation and are arguing that Duke should either buy their plant (Calpine) or enter into long-term electricity supply contracts. Calpine in particular is keen to sell its 10 year old 550MW combined-cycle plant at Osprey in central Florida which was built in anticipation of high growth rates that never quite emerged, with consequently diluted returns.

 

Duke’s arguments

 

Duke has inter alia argued that…

 

·     Because Osprey is now 10 years old, it will be less efficient than the new generation proposed by Duke.

 

·     Additional transmission grid investment would be required to transmit Osprey’s generation to Duke’s retail market, whilst Crystal River is already within Duke’s retail market.

 

Possible regulatory responses

 

The PSC’s responses are limited to either approving or disallowing Duke’s (self-) build option ... it cannot instruct Duke to buy existing plant or to buy long-term generation contracts. The PSC will be considering Duke’s application over the next few months, so Pipes & Wires will check back to see what answer they came up with.

 

US – Dynergy agrees to buy generation plants

 

Introduction

 

Pipes & Wires has closely followed recent mergers in the US power industry (refer below). This article examines the recent news that Dynergy has agreed to buy 12,500MW of coal and gas-fired generation from Duke Energy and from Energy Capital Partners.

 

Recent deals

 

Recent big deals in the US include…

 

Deal

Dimensions of merged entity

Consideration

Status

PPL’s acquisition of LG&E and KU (from E.On US)

20,000MW of generation, 2,600,000 electric customers

$5.6b cash and $800m debt

 

Completed in November 2010.

First Energy Corp acquires Allegheny Energy

23,700MW of generation, 6,000,000 electric customers, annual revenue of $16b.

$4.4b in stock and $3.8b debt

 

Completed in February 2011.

Northeast Utilities acquisition of NStar

3,000,000 electric and 505,000 gas customers, annual revenue of $8.4b.

 

$4.17b in stock

 

Completed in April 2012.

Duke Energy’s acquisition of Progress Energy

56,000MW of generation, 7,100,000 electric customers.

$13.8b in stock and $12.2b debt

 

Completed in July 2012.

AES’s acquisition of DPL

 

Annual revenue of $19b, 970,000 electric customers.

 

$3.5b cash

Completed in December 2011.

Exelon’s bid for Constellation

44,000MW of generation, 6,600,000 electric customers, annual revenue of $33b.

 

$7.7b in stock

Completed in March 2012.

Exelon’s bid for Pepco

About 9,800,000 customers

$6.8b in cash.

Regulatory applications in progress as of August 2014.

 

Dynergy’s existing footprint

 

Dynergy’s existing footprint includes 13,120MW of generation plants in California, Pennsylvania, Illinois, New York and Maine. These plants operate within 5 separate ISO jurisdictions (Mid-West, New England, New York, PJM and California). 

 

The proposed generation acquisitions

 

Dynergy’s proposed generation acquisitions include…

 

·     Duke Energy’s retail electric business in Ohio, Pennsylvania and Michigan, along with 6,100MW of generation capacity within the PJM’s footprint. The consideration will be $2.8b.

 

·     Energy Capital Partners 6,300MW of generation capacity within the New England ISO and the PJM footprints. The consideration will be $3.45b.

 

These acquisitions will expand Dynergy’s generation capacity to 25,500MW.

 

Possible strategies

 

Possible strategies behind Dynergy’s acquisitions include…

 

·     A sharp increase in wholesale prices in the New England ISO as the withdrawal of about 3,100MW of generation capacity by 2017 is announced, with only 600MW of demand response being available.

 

·     A change in the PJM rules requiring generators to be capable of sustained, reliable performance in the face of cold winter weather.

 

Both of these market issues have led to expected increases in wholesale prices, prompting investment. Dynergy expects both deals to be completed by the end of March 2015.

 

US – progress on the Exelon – Pepco deal

 

Introduction

 

Pipes & Wires #134 examined Exelon’s proposed acquisition of Pepco, and noted that a range of regulatory approvals were being sought. This article quickly re-caps the deal and examines progress on those approvals.

 

A bit about Exelon and Pepco

 

Exelon is among the largest of America’s electric companies, with about 35,000 MW of generation supplying about 7,800,000 customers through its subsidiaries Baltimore Gas & Electric, Commonwealth Edison and the Philadelphia Electric Company (PECO). Annual revenues are about $25b.

 

Pepco Holdings supplies about 2,000,000 electric and gas customers in the Delaware, Washington DC, Maryland and New Jersey areas through its regulated subsidiaries Pepco, Delmarva Power and Atlantic City Electric.

 

If the merger is successful, the combined electric and gas companies will supply about 9,800,000 customers.

 

Key features of Exelon’s offer

 

Exelon has made a $6.8b all-cash offer of $27.25 per Pepco share, which represents a 24.7% premium to Pepco’s closing price on the announcement day.

 

The required approvals

 

The following regulatory approvals are currently being sought…

 

Regulator

Current status of approval

Federal Energy Regulatory Commission.

 

Application filed on 30th May.

District of Columbia Public Service Commission.

 

Application filed on 18th June.

Delaware Public Service Commission.

 

Application filed on 18th June.

Maryland Public Service Commission.

 

Application filed on 19th August, approval may take up to 15 months.

New Jersey Board of Public Utilities.

 

Application filed on 18th June.

Virginia State Corporation Commission.

 

Commission staff recommended on 18th August that the merger proceed subject to 2 conditions (mainly around regulatory reporting, which Pipes & Wires would’ve thought were a given anyway).

 

Pipes & Wires will revisit this deal as the various approvals emerge … could take a while though.

 

UK & Europe

 

UK – the RIIO-ED1 Draft Decisions

 

Introduction

 

The UK gas & electricity regulator OFGEM recently announced its Draft Decisions that will apply to the 14 electricity distribution licenses in England, Wales and Scotland for the 8 year period commencing on 1st April 2015. This article summarises those Draft Decisions.

 

Assessing the DNO’s business plans

 

Each of the 6 distribution network operators (DNO’s) submitted a business plan for each of its distribution licenses setting out the customer and regulatory outcomes it proposed to deliver for the 8 year control period.

 

In November 2013 OFGEM fast-tracked approval of Western Power Distribution’s 4 business plans (South Western, South Wales, Midlands and East Midlands) as they were judged to provide customers with sufficient value for money. The business cases presented by …

 

·     Electricity North West (North Western)

 

·     Northern Power Grid (Northern and Yorkshire)

 

·     UK Power Networks (London, Eastern and South Eastern)

 

·     Scottish & Southern (Scottish Hydro and Southern)

 

·     SP Energy Networks (Scottish and MANWEB)

 

were returned for further work due to deficiencies in areas such as cost efficiencies, process weaknesses and risk allocation.

 

Key features of the Draft Decisions

 

Key features of the Draft Decisions include the DNO’s identifying cost savings of £700m with OFGEM disallowing a further £1.4b of costs. The total costs for the 8 years and the expected average annual bill reduction are shown for each DNO below…

 

DNO

Total spend for 8 years

Spend per line km

Spend per customer

Average bill decrease

Western Power Distribution

£7.1b

£22,591

£917

£9

Electricity North West

£1.8b

£25,700

£758

£26

Northern Power Grid

£2.9b

£23,859

£750

£13

UK Power Networks

£6.0b

£25,829

£739

£5

Scottish & Southern

£3.4b

£18,589

£909

£20

SP Energy Networks

£3.2b

£20,494

£916

£12

 

Next steps

 

OFGEM is currently consulting on these Draft Decisions and expects to publish its Final Decisions in November 2014.

 

Australia

 

Queensland – reconciling solar with distribution pricing

 

Introduction

 

Recently I’ve encountered a couple of articles discussing the dilemma facing electric companies who have increasing amounts of rooftop solar connected to their networks but are required to recover the fixed costs of that network on a nett kWh basis ... certainly not a new theme, but coming at what seems to be a quickened pace. This article picks on a recent change in distribution pricing methodology in the Australian state of Queensland as a starting point for exploring pricing issues.

 

The new pricing scheme

 

The new pricing scheme approved by the Queensland Competition Authority (QCA) in June 2014 will inter alia remove the $0.082 feed-in tariff, and will instead enable rooftop solar owners to negotiate the price that they will be paid for exported electricity. The solar industry is understandably concerned about the removal of the feed-in tariff, and that is what appears to get the media attention.

 

Thinking through the issues … beating that same old drum … again !!

 

It seems that underneath this there is a determined unwillingness to accept that one way or another a distribution network that recovers its high fixed costs with nett kWh prices provides a subsidy for those who import (consume) fewer kWh from the network. An argument raised by the solar energy industry is along the lines of “if more and more people reduce their demand for electricity, are they (the distribution companies) going to increase their costs even more next year and the year after ?” The short answer is “no” … they won’t be increasing their costs. What they might be increasing is their prices to recover those costs, interestingly enough as a result of increasing rooftop solar penetration.

 

Some possible policy directions

 

It would therefore seem that we need some clear policy direction from government on the following issues…

 

·     An acknowledgement that distribution networks have a high fixed cost that is almost totally independent of kWh throughput.

 

·     That recovering those high fixed costs on a kWh (variable) basis is economically inefficient, and whilst it worked well enough when almost all customers imported from the network, the prices necessary to recover those costs from a declining kWh consumption will have to increase.

 

·     Whether electric companies can adopt a more analytically sound approach of fixed prices, and if they can’t, a clear policy statement acknowledging that some other (economically inefficient) approach is preferred.

 

·     Whether subsidies are acceptable or not. Given that subsidies for the oil and nuclear industries are apparently no longer acceptable, maybe we need to ask why subsidies for renewables are acceptable.

 

·     If it is considered that subsidies for renewables are acceptable, then who should pay those subsidies ? The policy makers seem silent on this one, with the practical effect being that those electric consumers who don’t generate their own electricity are simply left paying a subsidy to those who do.

 

General stuff

 

Guide to NZ electricity laws

 

I’ve compiled a “wall chart” setting out the relationship between various past and present electricity Acts, Regulations, Codes etc in sort of a chronological progression. To request your free copy, pick here. It looks really cool printed in color as an A2 or A1 size.

 

Recently released book “Small Hydroelectric Engineering Practice”

 

Well-known hydroelectric engineer Bryan Leyland has recently published a book entitled “Small Hydroelectric Engineering Practice”. This is a comprehensive reference book covering all aspects of identifying, building and operating hydroelectric schemes between 500kW and 50MW. Pick here for more details.

 

A bit of light-hearted humor

 

What if price control had been around in the 1920’s and 1930’s ? A collection of photo’s with humorous captions looks at some of the salient features of price control. Pick here to download.

 

Conferences & training courses

 

The following conferences and training courses are planned...

 

·     Fundamentals of the NZ Electricity Industry – Wellington, 23rd – 24th September 2014.

 

·     Fundamentals of the NZ Electricity Industry – Auckland, 7th – 8th October 2014.

 

·     Africa Oil & Gas Expo – Johannesburg, 9th – 10th October, 2014.

 

Utility Consultants takes no responsibility for the content of individual courses or conferences, nor for any administrative or travel arrangements.

 

Wanted – old electricity history books

 

If anyone has an old copy of the following books (or any similar books) they no longer want I’d be happy to give them a good home…

 

·     Wonders Of World Engineering (published 1937) – in particular editions 1 to 27.

 

·     Distribution Of Electricity (WT Henley, the cable manufacturer)

 

·     Northwards March The Pylons.

 

·     Two Per Mile.

 

·     Live Lines (the old ESAA journal).

 

·     The Engineering History Of Electric Supply In New Zealand.

 

House-keeping stuff

 

Opt out from Pipes & Wires

 

Pick this link to opt out from Pipes & Wires. Please ensure that you send from the email address we send Pipes & Wires to.

 

Disclaimer

 

These articles are of a general nature and are not intended as specific legal, consulting or investment advice, and are correct at the time of writing. In particular Pipes & Wires may make forward looking or speculative statements, projections or estimates of such matters as industry structural changes, merger outcomes or regulatory determinations. These articles also summarise lengthy documents, and it is important that readers refer to those documents in forming opinions or taking action.

 

Utility Consultants Ltd accepts no liability for action or inaction based on the contents of Pipes & Wires including any loss, damage or exposure to offensive material from linking to any websites contained herein, or from any republishing by a third-party whether authorised or not, nor from any comments posted on Linked In, Face Book or similar by other parties.