Pipes & Wires

THE JOURNAL OF COOL ENERGY & UTILITIES STUFF

Issue 123 – June 2013

 

From the editor’s desk…

 

Welcome to Pipes & Wires #123. This month we start by examining Orion’s CPP application, and then look at the Kenyan governments’ refusal to allow electricity tariff increases. We then look at plans to further liberalise the Japanese electricity market, and then we look at some regulatory approvals in the US.

 

Then it’s on to Europe to examine the ongoing disputes over who pays for renewable support and over what an acceptable WACC is, along with a possible network sale. We end this issue with a look at the final water & sewage determination in South Australia.

 

Matters for attention (NZ)

 

Distribution pricing review

 

The Electricity Authority will be reviewing EDB’s pricing methodologies to inter alia ensure that each EDB’s methodology aligns to the pricing principles and is efficient. This work stream will involve an independent review of each EDB’s methodology, after which the Authority will release its findings, probably around August or September 2013.

 

The Authority’s focus will be on whether distribution pricing is efficient and is supporting competition. Pick here or call Phil on (07) 854-6541 to discuss your requirements.

 

Gas asset management plans

 

The Commerce Commission’s decisions NZCC 23 and NZCC 24 set out the requirements for gas distribution and gas transmission businesses (collectively referred to as gas pipeline businesses, GPB’s) to disclose an AMP that meets specified criteria. Pick here or call Phil on (07) 854-6541 to discuss your requirements.

 

Information disclosure updates

 

The Commerce Commission has recently posted further material on electricity information disclosure. Pick here or call Phil on (07) 854-6541 to discuss how your company might comply with these requirements.

 

New Zealand

 

NZ – update on Orion’s CPP application

 

Introduction

 

Canterbury-based electricity distribution company Orion recently applied to the Commerce Commission for a customised price path (CPP) to fund recovery work from the February 2011 earthquake. This article examines CPP’s and looks at some of the key features of Orion’s application.

 

Legal framework

 

The regulatory framework for electricity distribution companies is set out in Part 4 of the Commerce Act 1986, with Subpart 6 dealing specifically with CPP’s. A non-exempt electricity distribution company (subject to a Default Price Path) can apply for a CPP if it believes that it cannot adequately fund its activities under the DPP.

 

Orion’s unique circumstances

 

Prior to submitting a CPP application, Orion had sought an exemption from Part 4 under earthquake recovery legislation by way of an Order in Council (OIC) to recover the costs from the earthquake. Unfortunately the OIC was unsuccessful.

 

Key features of the application

 

Key features of Orion’s CPP application include....

 

·           A forecast CapEx that is $155m greater than pre-earthquake estimates.

 

·           A step increase in prices of CPI + 15% on 1st April 2014, followed by CPI + 1.2% for the following 4 years.

 

Pick here to watch a video clip describing the CPP application

 

The Commission’s assessment process

 

Because of the tight statutory timeframe for assessing CPP applications, the Commission requires applicants to engage a mutually acceptable independent verifier to confirm that the application fulfils the CPP requirements. This is in contrast to many other jurisdictions in which the regulator engages various consultants after receiving the application.

 

Next steps

 

The Commission is currently assessing Orion’s application, and expects to publish a draft determination on 9th August 2013 followed by a final determination on 29th November 2013. Pipes & Wires will comment further as those determinations are made public.

 

Africa

 

Kenya – prohibiting the planned electricity tariff increases

 

Introduction

 

Pipes & Wires #120 examined the Kenya Power & Lighting Company’s (KPLC) proposed tariff increases that were supported by the Energy Regulatory Commission (ERC). This article examines the newly elected governments’ decision to prohibit the proposed tariff increase.

 

Background

 

KPLC had proposed some significant industrial and domestic tariff increases to fund almost US$1b of transmission and distribution spend. The ERC supported this proposed tariff increases, noting that KPLC has absorbed past operating cost increases.

 

The governments’ response

 

In May 2013 the newly elected government indicated that it will not allow the planned tariff increases to proceed, but that KPLC must instead “sort out its inefficiencies”. Electricity tariffs have not been reviewed since 2008, despite industry regulations providing for reviews every 3 years. The reasons given for suspending the last 3 reviews include...

 

·           2011 – Claims that high inflation would’ve been exacerbated if electricity tariffs were allowed to increase.

 

·           2012 – A general election was pending.

 

·           2013 – Deeper consideration of stakeholder views was required.

 

Likely scenarios

 

There are really only 3 scenario’s available to an under-funded electric company...

 

·           Spend at the proposed level, and fund from a combination of new equity, debt, retained earnings or shareholder subsidy.

 

·           Spend at the proposed level, and rely on government subsidies or bail-outs.

 

·           Match spending to the allowable revenue. This will mean that new generation and grid improvements will be unlikely to proceed.

 

It doesn’t require much thought to see that none of these scenarios are sustainable.

 

Wider implications

 

What might some of the wider implications be ? Here are a few possibilities to start with....

 

·           The ERC is obviously not as independent and free from political intervention as most of us understand a regulator to be.

 

·           Notwithstanding established legal appeal processes, the industry apparently cannot treat a regulatory determination as the last word.

 

·           Investors in the proposed liberalisation of Kenya’s energy markets will probably be spooked.

 

·           Listed companies in the wider Kenyan economy are likely to be spooked.

 

·           The lights will probably go out, undermining Kenya’s economy.

 

So on the face of it, things look pretty difficult for KPLC and for the wider Kenyan economy.

 

Asia

 

Japan – further liberalisation introduced to Parliament

 

Introduction

 

Legislation was recently submitted to Parliament to further liberalise Japan’s electricity markets. This article examines the liberalisation to date and the key features of the legislation.

 

Liberalisation so far

 

Key features of the liberalisation so far include....

 

·           Phase 1 in 1995 allowed Independent Power Producer’s (IPP’s) to enter the generation market. Some oversight of retail tariffs and costs was also introduced.

 

·           Phase 2 in 1999 introduced competition for customers taking more than 2MW demand. Associated rules for transmission access were also established.

 

·           Phase 3 in 2003 extended competition for customers taking more than 500kW demand.

 

It was decided not to liberalise the domestic electricity market in 2008 (which would’ve represented Phase 4) as the benefits seemed doubtful.

 

Key features of the legislation

 

Key features of the legislation include....

 

·           Establishing a nation-wide grid operator in 2015, with authority over real-time generation dispatch. This will presumably have to consider the limit of 1,500MW transfer capacity of the 4 back-to-back convertors that interconnect the 50Hz grid in the east and the 60Hz grid in the west.

 

·           Establish a separate electricity regulator in 2015. Many policy and regulatory functions are currently performed by the Ministry of Trade & Industry.

 

·           Plans to introduce legislation in 2014 to introduce competition into the domestic market in 2016.

 

·           Plans to introduce legislation in 2015 to require operational and financial separation of lines and energy by about 2018. This would appear to stop short of full ownership separation.

 

·           Abolition of all price controls by about 2018 (presumably only retail price controls).

 

It appears that the current government-ordered disaggregation of the Tokyo Electric Power Company (TEPCO) is a model for the legislation.

 

The editor comments

 

What do we make of this ? One aspect of the popular liberalisation approach that never seems to be discussed is that if a market is created in the face of a shortfall of supply, prices will rise and may well offset any benefits from competition (we’ve seen something along these lines happen in New Zealand and Ontario, and the opposite happen in England and Victoria when excess supply emerged). So does Japan have a shortage of electricity supply ? By June 2011 Japan’s reserve capacity margin declined to between 9% and 12% after substantial energy savings by customers and with 40% of the nuclear capacity still operating. It would appear that as demand recovers and nuclear plants are closed a shortfall of supply with respect to demand will emerge. So at a rough guess, I’d say prices will rise.

 

North America

 

US – approving the Laredo – Lower Rio Grande Valley line

 

Introduction

 

Pipes & Wires #107 examined the planned 163 mile 345kV line from Laredo to the Lower Rio Grande Valley in southern Texas, and noted that the Texas Public Utilities Commission assessment of the “criticality” of this line would be significant. This article examines the PUC’s recent approval of the application.

 

Re-capping the lines details

 

Key details of the line include....

 

·           The proposed 345kV line will stretch 163 miles from Lobo Substation near Laredo to substations north of Edinburgh in southern Texas, and is expected to cost $300m.

 

·           The owner of the proposed line is Electric Transmission Texas LLC, a joint venture between American Electric Power (AEP) and MidAmerican Energy Holdings.

 

·           The ERCOT expected to file a Certificate of Convenience and Necessity (CNN) application with the PUC in 2013 and complete the line in 2016.

 

The PUC’s approval

 

On 9th May the PUC unanimously approved ETT’s application for a CNN, including a settlement with about 100 effected landowners along the proposed line route. Understandably not everyone along the proposed line route is thrilled about it, with some law firms already offering to challenge the decision or improve the settlements.

 

Next steps

 

Detailed design and negotiations for land access are expected to start soon, with line construction beginning in 2014.

 

US – smart meters get the go-ahead in Illinois

 

Introduction

 

Pipes & Wires #106 noted Governor Pat Quinn’s rejection of Senate Bill 1652 despite both chambers of the General Assembly passing the Bill. This article examines the passing of the replacement Senate Bill 0009, which also had a rocky ride through Springfield’s corridors of power.

 

Re-capping progress on the Bills

 

SB 1652 would’ve provided stronger mechanisms for electric companies like Commonwealth Edison to recover the costs of smart meter roll-out. Quinn’s rejection claimed that the Bill would result in “excessive financial burden on consumers, sweetheart deals, and no guarantee of improved service”.

 

SB 1652 was subsequently replaced by SB 0009 which clarified some wording, and was passed into law as the General Assembly over-rode a veto.

 

ComEd’s roll-out begins

 

ComEd expects to start rolling out smart meters in late 2013 in a program that it expects to complete in 2021. The expected benefits include reducing about 700,000 outages per year which are estimated to cost customers about $100m.

 

UK and Europe

 

Germany – paying for renewable support

 

Introduction

 

Pipes & Wires #119 examined the disquiet around who should pay for Statkraft’s 800MW Knapsack #1 gas-fired plant near Cologne to provide standby MW. This article continues that theme by looking at how E.On is operating its Irsching units #4 and #5 to provide grid stability.

 

The Irsching units

 

Irsching is a long-established generation site dating back to the late 1960’s, although units #1 and #2 have already been decommissioned. The units that are providing grid stability are...

 

·           Unit #4 – a 570MW gas-fired combined-cycle.

 

·           Unit #5 – an 860MW gas-fired combined cycle.

 

The issue

 

The increasing penetration of renewables has led to increasingly intermittent generation, which must be supported by quick-start plant. The added extra to this is that grid operators such as TenneT are required by the Renewable Energy Act to give priority to purchasing and transmitting renewable energy.

 

As we saw with Knapsack, the generated MWh doesn’t adequately fund the high fixed costs of maintaining quick-start generation. Accordingly, E.On had planned to suspend Irsching’s operation which it said would result in higher costs to electric consumers.

 

The agreement to continue operating

 

E.On and TenneT recently hammered out an agreement that also has the support of the Federal Network Agency (BNetzA) that fixed costs will be paid to quick-start generation that are operated on demand from grid operators for more than 10% of the time. It was also agreed that E.On would not close Irsching #4 or #5 for at least 3 years.

 

The real policy issue

 

As Pipes & Wires #119 commented, there seems to be a huge disconnect between the “must have” security of supply that authorities clearly recognise, and the need for standby generators to be paid for providing that security of supply. It is therefore very pleasing to see an energy agency recognising that the high fixed costs of standby plant actually do need to be paid for.

 

Finland – selling the grids ?

 

Introduction

 

News recently emerged that state-controlled Fortum is exploring the sale of its network businesses. This article examines the proposed sale, and also looks at the wider trend of network sales and where it might lead

 

A bit about Fortum

 

Fortum is an electricity, gas and heat company that operates in the Nordic countries, Russia, Poland and the Baltic countries. Annual revenues are about €6.1b, and annual profit is about €1.8b. Fortum’s network business includes 156,000km of lines supplying 1,600,000 customers in Finland, Sweden and Norway.

 

Fortum’s strategy has a strong bias towards unregulated energy, similar to many other large energy companies such as E.On.

 

The proposed sale of the network businesses

 

In early 2013 Fortum decided to undertake a strategic review of future alternatives, including possible sale of the electricity networks (which would be aligned to its strategy). Although the distribution business is returning about 8% on nett assets, Fortum believes that its “value potential could be captured to the fullest extent in a different setting” ie. it might be better for us to cash-out of the network business and let a player focused on the distribution sector own the networks.

 

What would a sale look like ?

 

Initial estimates of a likely sale price are about €5b, or about €3,100 per customer (which seems in line with other distribution network sales). Fortum has appointed CitiBank and Danske Bank to explore possible sale options, with industry gossip suggesting a sale is the most likely option.

 

The wider trends

 

There seems to be a couple of trends at work here....

 

·           The need to reduce debt, generally by selling assets.

 

·           The need to separate lines and energy to comply with the EU Third Package.

 

·           A widening gap between traditional electric and gas companies who are focusing on unregulated energy opportunities and markets, and investment funds who are increasingly owning regulated pipes & wires.

 

Pipes & Wires will re-visit Fortum as news emerges.

 

Germany – the battle for WACC

 

Introduction

 

Pipes & Wires #74 noted that the German energy regulator Bundesnetzagentur (BNetzA) decreed a pre-tax cost of equity of 9.29% for new assets and 7.56% for legacy assets, ostensibly to incentivise new investment. This article examines a preliminary court decision to those rates, and also looks at the rates the BNetzA proposes to apply for the forthcoming regulatory periods.

 

Basis of the legal appeal

 

Several gas and electric companies appealed the BNetzA’s 9.29% pre-tax cost of equity for the 2008 – 2013 regulatory period, claiming that it was too low to encourage investment and that about 11% would be more appropriate. Several gas companies also claimed that gas businesses should be allowed an even higher pre-tax cost of equity because they face additional investment risks.

 

The Court’s preliminary ruling

 

The Dusseldorf Higher Regional Court confirmed that firstly the BNetzA’s approach to calculating the pre-tax cost of equity was appropriate, and secondly that the determined rates were adequate. These rulings were not binding as the applicants had 1 month to file an appeal.

 

Proposed rates for the forthcoming regulatory periods

 

The BNetzA is proposing 9.05% for new assets and 7.14% for legacy assets for the 2014 – 2018 electricity price control and for the 2013 – 2017 gas control period.

 

Australia

 

SA – the final water & sewage tariff determination

 

Introduction

 

Pipes & Wires #118 and #120 discussed the water & sewage determination that will apply in South Australia from 1st July 2013 to 30th June 2016. This article concludes that discussion by examining the Essential Services Commission of South Australia’s (ESCOSA) Final Determination.

 

Key features of the Final Decision

 

Key features of the Final Determination are set out below.

 

Parameter

Proposal

Draft Decision

Final Decision

CapEx

$1,100m

$963m

$983m

OpEx

$1,400m

$1,280m

$1,268m

Opening asset base

$7,700m water

$3,580m sewage

To be stated in Final Decision

$7,767m water

$3,584m sewage

Nominal vanilla WACC

7.98%

Use of NV WACC disallowed

Use of NV WACC disallowed

Real vanilla WACC

5.57%

4.87%

4.5%

 

This ends Pipes & Wires coverage of the SA water & sewage tariff determination.

 

General stuff

 

Consulting services that may be of interest to clients

 

Utility Consultants wide expertise extends well beyond the above projects ... if you need energy network advice chances are Utility Consultants has done work in that area. Here’s a sample of work done for clients over the last few years that demonstrate the breadth of skills, insight and experience that is available....

 

·       Advised an electricity business on the regulatory implications of bringing externally contracted field services back in-house.

 

·       Identified economic and regulatory arguments to support inclusion of transmission interconnection charge risk into network tariffs.

 

·       Advised lines businesses on a regulator’s proposed treatment of CapEx and OpEx.

 

·       Advised an international investor on gas distribution policy and regulatory trends.

 

·       Identified national energy policy implications for lines businesses.

 

·       Assisted a lines business to identify the burden of proof implied by regulatory determinations.

 

·       Suggested amendments to a gas transmission AMP to strengthen the economic arguments.

 

·       Identified electricity network investment characteristics as part of an acquisition study.

 

·       Developed an AM framework for a gas distribution business to link AM to regulatory requirements.

 

·       Identified OpEx CapEx tradeoffs for an electricity lines business.

 

·       Performed various substation growth and reinforcement assessments.

 

·       Performed network physical and business risk studies.

 

·       Compiled disaster recovery and business continuity plans.

 

Pick here to download a profile of recent projects, or here to contact Phil.

 

Guide to NZ electricity laws

 

I’ve compiled a “wall chart” setting out the relationship between various past and present electricity Acts, Regulations, Codes etc in sort of a chronological progression. To request your free copy, pick here.

 

A bit of light-hearted humor

 

What if price control had been around in the 1920’s and 1930’s ? A collection of photo’s with humorous captions looks at some of the salient features of price control. Pick here to download.

 

Conferences & training courses

 

The following conferences and training courses are planned...

 

·       PAS 55 training course – Sydney, 25th – 26th June 2013.

 

·       PAS 55 training course – Sydney, 16th – 17th July 2013.

 

·       ACCC / AER Regulatory Conference – Brisbane, 25th – 26th July 2013.

 

·       Fundamentals of the NZ electricity industry – Auckland, 2nd – 3rd September 2013.

 

·       Fundamentals of the NZ electricity industry – Wellington, 16th – 17th September 2013.

 

·       CIGRE International Symposium – Auckland, 16th – 17th September 2013.

 

Utility Consultants takes no responsibility for the content of individual courses or conferences, nor for any administrative or travel arrangements.

 

Wanted – old electricity history books

 

If anyone has an old copy of the following books (or any similar books) they no longer want I’d be happy to give them a good home…

 

·       Wonders Of World Engineering (published 1937) – in particular editions 1 to 27.

 

·       Distribution Of Electricity (WT Henley, the cable manufacturer)

 

·       White Diamonds North.

 

·       Northwards March The Pylons.

 

·       Two Per Mile.

 

·       Live Lines (the old ESAA journal).

 

·       The Engineering History Of Electric Supply In New Zealand.

 

House-keeping stuff

 

Opt out from Pipes & Wires

 

Pick this link to opt out from Pipes & Wires. Please ensure that you send from the email address we send Pipes & Wires to.

 

Disclaimer

 

These articles are of a general nature and are not intended as specific legal, consulting or investment advice, and are correct at the time of writing. In particular Pipes & Wires may make forward looking or speculative statements, projections or estimates of such matters as industry structural changes, merger outcomes or regulatory determinations. These articles also summarise lengthy documents, and it is important that readers refer to those documents in forming opinions or taking action.

 

Utility Consultants Ltd accepts no liability for action or inaction based on the contents of Pipes & Wires including any loss, damage or exposure to offensive material from linking to any websites contained herein, or from any republishing by a third-party whether authorised or not, nor from any comments posted on Linked In, Face Book or similar by other parties.