Pipes & Wires

THE JOURNAL OF COOL ENERGY & UTILITIES STUFF

Issue 119 – February 2012

 

From the editor’s desk…

 

Welcome to Pipes & Wires #119. This month we start by examining some critical asset management issues, and then move on to some regulatory developments in the NZ gas pipes sector. We look at water pricing in the UK, paying for standby generation in Germany and easing electricity regulatory pressure in the UK. We then take a quick look at a regulatory decision in Australia and conclude with some storm recovery and smart grid happenings in the US.

 

General stuff

 

Consulting services that may be of interest to clients

 

Utility Consultants wide expertise extends well beyond the above projects ... if you need energy network advice chances are Utility Consultants has done work in that area. Here’s a sample of work done for clients over the last few years that demonstrate the breadth of skills, insight and experience that is available....

 

·       Advised an electricity business on the regulatory implications of bringing externally contracted field services back in-house.

 

·       Identified economic and regulatory arguments to support inclusion of transmission interconnection charge risk into network tariffs.

 

·       Advised lines businesses on a regulator’s proposed treatment of CapEx and OpEx.

 

·       Advised an international investor on gas distribution policy and regulatory trends.

 

·       Identified national energy policy implications for lines businesses.

 

·       Assisted a lines business to identify the burden of proof implied by regulatory determinations.

 

·       Suggested amendments to a gas transmission AMP to strengthen the economic arguments.

 

·       Identified electricity network investment characteristics as part of an acquisition study.

 

·       Developed an AM framework for a gas distribution business to link AM to regulatory requirements.

 

·       Identified OpEx CapEx tradeoffs for an electricity lines business.

 

·       Performed various substation growth and reinforcement assessments.

 

·       Performed network physical and business risk studies.

 

·       Compiled disaster recovery and business continuity plans.

 

Pick here to download a profile of recent projects, or here to contact Phil.

 

Guide to NZ electricity laws

 

I’ve compiled a “wall chart” setting out the relationship between various past and present electricity Acts, Regulations, Codes etc in sort of a chronological progression. To request your free copy, pick here.

 

A bit of light-hearted humor

 

What if price control had been around in the 1920’s and 1930’s ? A collection of photo’s with humorous captions looks at some of the salient features of price control. Pick here to download.

 

Conferences & training courses

 

The following conferences and training courses are planned...

 

·       Electricity Industry Fundamentals – Wellington, 18th – 19th March 2013.

 

·       ACCC / AER Regulatory Conference – Brisbane, 25th – 26th July 2013.

 

·       Infrastructure, Investment & Regulation Conference – Sydney, 30th – 31st May 2013.

 

·       CIGRE International Symposium – Auckland, 16th – 17th September 2013.

 

Wanted – old electricity history books

 

If anyone has an old copy of the following books (or any similar books) they no longer want I’d be happy to give them a good home…

 

·       Wonders Of World Engineering (published 1937) – in particular editions 1 to 27.

 

·       White Diamonds North.

 

·       Northwards March The Pylons.

 

·       Two Per Mile.

 

·       Live Lines (the old ESAA journal).

 

·       The Engineering History Of Electric Supply In New Zealand.

 

Global

 

Optimising asset management

 

Introduction

 

As I work with many electric companies and read a lot of articles and listen to a few podcasts, it seems that asset management in the electricity sector (and indeed in other infrastructure sectors) seems to be facing a few common frontiers. These frontiers appear to be...

 

Increased regulatory scrutiny of CapEx

 

Recent years have seen significant uplifts in forecast CapEx, both from aging assets requiring renewal and to restore capacity and security headroom. In the case of transmission grids and pipelines, the CapEx is also usually lumpy ie. consists of a small number of large projects.

 

In many (but certainly not all) cases those forecasts have been significantly reduced in the regulators’ draft and final decisions. I’m getting a sense that some regulators are not fully comfortable with such significant forecast uplifts and seem to be placing undue emphasis on previous regulatory periods (noting that some jurisdictions require the regulator to “have regard” to the forecasts from previous periods).

 

Interfacing detail design with physical works delivery

 

Most infrastructure companies seem very good at detail design, and also seem to have a good handle on physical delivery of the works. The fuzzy activity between the two ... often called “project planning” or “works delivery” seems to be the uneasy bedfellow, and yet it also seems to be the most critical activity along the project delivery chain.

 

I’ve observed this “works delivery” activity being embodied within engineering design, standing alone as a third party, being attached to the construction function, being out-sourced to contractors, and being attached to the end of asset management. Probably the best model appears to be a specialist works delivery function at the tail of the asset management activity, giving a high degree of control to the client rather than the contractor and ensuring a close but none-the-less delineated relationship with asset management and detail design.

 

Improved asset condition data to support renewal modeling

 

As noted above, regulators seem uncomfortable with the significant uplifts in renewal CapEx being proposed by many infrastructure companies. Asset condition is obviously a key driver of renewal spend, but as most of us know, determining the precise condition (and hence remaining life) of a sealed or buried asset is difficult at best. Despite an increasing number of sophisticated scientific tests available for determining asset condition I’m not sure that we are getting close to accurate answers that will in turn lead to absolutely defensible renewal profiles.

 

Perhaps another angle on this is to consider asset criticality (and I know many are doing this already), and make a judgment call that for critical assets it is better discard some unconsumed asset life rather than risk an in-service failure and possible health and safety consequences.

 

To discuss these issues further, pick here or call Phil on +64-7-8546541

 

New Zealand

 

NZ – disclosure of gas AMP’s

 

Introduction

 

Electricity distribution businesses (EDB’s) have had to publically disclose an asset management plan (AMP) since March 2000, with several revisions to the requirements that embody some themes (ask me about this). Much more recently, the Commerce Commission’s decisions NZCC 23 and NZCC 24 set out the requirements for gas distribution and gas transmission businesses (collectively referred to as gas pipeline businesses, GPB’s) to disclose an AMP that meets specified criteria.

 

Legal framework

 

The legal framework for an information disclosure regime is set out in Subpart 4 of Part 4 of the Commerce Act 1986. Subpart 10 of Part 4 (s55c) provides for all gas pipeline services to be subject to information disclosure.

 

AMP disclosure requirements

 

The specific disclosure requirements for both gas distribution and gas transmission are set out as follows...

 

·       Section 2.6 of each decision sets out the various broad requirements that an AMP must meet, such as contributing to the Part 4 Purpose Statement, and being able to be understood by someone with a basic knowledge of infrastructural asset management.

 

·       Section 2.6 sets out the dates by which each GPB must disclose its’ AMP. Care is required, as the dates are based on several defined terms that much be well understood.

 

·       Section 2.6 also describes the various forecasts (Schedules 11a to 12b that include CapEx, OpEx, asset condition and demand).

 

·       Attachment A sets out the specific clause-by-clause requirements that the AMP must include.

 

·       The asset management maturity assessment tool (AMMAT) in Schedule 13 must also be completed and disclosed.

 

These requirements are almost identical to the disclosure requirements for electricity AMP’s.

 

Next steps

 

Utility Consultants has advised 11 EDB’s on their AMMAT obligations and 22 EDB’s on their AMP obligations, and is therefore well placed to advise GPB’s on their AMP’s and AMMAT’s. Pick here or call Phil on (07) 854-6541 to discuss your requirements.

 

NZ – cost of capital for the Maui Pipeline

 

Introduction

 

Recent issues of Pipes & Wires have examined the weighted average cost of capital (WACC) that will apply to various gas distribution and transmission businesses (Pipes & Wires #116 and #118). This article examines the Commerce Commission’s recent WACC Determination that will apply to Maui Developments Ltd for the 2014 Disclosure Year (which commences on 1st January 2013).

 

What exactly does Maui do ?

 

In addition to owning the Maui Pipeline, Maui Developments also performs 3 operator roles...

 

·       Technical and engineering operation of the actual pipeline.

 

·       Commercial operation of various contracts and regulatory requirements specific to the pipeline.

 

·       System operator functions such as balancing, reconciliation, coordination and contingency management.

 

Legal framework

 

The WACC determinations have been made pursuant to Subpart 4 of Part 2 of the Gas Transmission Services Input Methodologies Determination 2012, which has in turn been compiled pursuant to Subpart 3 of Part 4 of the Commerce Act 1986.

 

The determination

 

The Commission has determined that the following WACC’s will apply for the 5 year period commencing on 1st January 2013...

 

WACC definition

Mid-point WACC value

25th percentile

75th percentile

Vanilla

6.65%

5.84%

7.46%

Post-tax

5.99%

5.18%

6.80%

 

UK and Europe

 

UK – compiling the next water price control

 

Introduction

 

The UK water and sewage regulatory OFWAT has started compiling the price controls that will apply for the 2015 – 2020 control period, which forms the subject of this article. This follows on from OFWAT’s analysis of some very significant issues (Pipes & Wires #110).

 

OFWAT’s statement of principles

 

OFWAT acknowledges that since setting the last price limits in 2009 the UK’s water sector has changed significantly hence it was necessary to undertake a review of regulation that was both wide and deep. This review incorporated the findings of several other independent reviews into detail aspects of the water sector.

 

This has resulted in several “price limit principles” being promulgated...

 

·       Targeting price control appropriately, including using different regulatory tools for different parts of the business and reducing or removing regulation where it becomes unnecessary.

 

·       Using a risk-based approach to compliance to reduce regulatory burden.

 

·       Developing clearer incentives that better drive economic efficiency.

 

·       Setting price controls that make companies more accountable for delivering customer needs.

 

·       Designing regulatory tools that are flexible and responsive.

 

·       Ensuring that regulation is transparent and predictable.

 

OFWAT’s proposed framework

 

Probably the most significant feature of OFWAT’s proposed framework is a visible separation of the controls that will apply to the wholesale water activities and the retail water activities, ostensibly forcing water and sewage businesses to better understand and respond to the price-quality trade-offs that customers want. Other features of the framework include setting default tariffs and service levels, and examination of total costs.

 

Next steps

 

OFWAT is receiving submissions on the proposed framework until 26th March 2013, with a final decision on the methodology expected about mid-2013.

 

Germany – who should pay for standby generation, and how ?

 

Introduction

 

Debate is increasing in Germany over who should pay for standby generation, and exactly what the payment mechanism should be. This article considers 2 contrasting viewpoints, and also touches on the complexity of national v’s regional solutions.

 

The key issues

 

Standby generation is being increasingly used to buffer intermittent wind power, so the GWh generated by the standby plants are declining. To pick on an example quoted in the media, the 800MW Knapsack #1 gas-fired plant near Cologne generated only 1,000GWh during 2012, down from 3,000GWh in 2011 and much less than its full capacity of 6,000GWh per year. The key issues are...

 

·       The basis for payment is still MWh, not peak MW.

 

·       There is a political desire for security of supply, albeit a desire that seems disconnected from the obvious question of “who pays for the security”.

 

The contrasting viewpoints

 

Just 2 contrasting viewpoints include...

 

·       Statkraft (the owner of Knapsack #1) is calling for a capacity payment of €15 per kW per year that should apply to all gas-fired plants (so Knapsack would receive about €12m per year). Statkraft argues this is less than 10% of the annual cost of “supporting” renewables.

 

·       E.On on the other hand has expressed concerns about capacity payments being based on national solutions, stating that capacity payments should be a last resort, be a harmonised EU-wide initiative, shouldn’t favor specific generation technologies and shouldn’t exclude any market participants.

 

So on the one hand we have a very pragmatic, fix-the-problem-now argument and on the other hand a seemingly theoretical and multi-pronged argument. Both arguments would appear to embody at least some self-interest.

 

The national v’s regional debate

 

Much has been made of harmonising the EU’s energy markets, so E.On’s view that any capacity payment mechanism needs to be consistent across the entire EU and not Germany makes some sense. However does that over-ride the need to fix a specific problem in Germany ?

 

The editor comments

 

As I see it there are several issues...

 

·       The seemingly huge disconnect between the “must have” security of supply and the need for standby generators to be paid for providing that security of supply.

 

·       The lack of clear progress on embedding payment mechanisms in electricity markets that reflect parameters other than short-run MWh.

 

·       The unwillingness to fix a national problem because we must fix it at a regional level.

 

·       The lingering distinction between subsidies paid to fossil-fired generators (bad) and the subsidies paid to renewables (okay).

 

So ... how’s this for a possible solution ? The principle of “exacerbater pays” is being considered by transmission grid companies ... if a connected party causes costs, they pay. Why not apply a similar approach to renewable generators ? Send a cost signal that provides an economic basis for either the renewable generator to reduce their impact on power fluctuations, or pays a third party to provide standby generation. After all we do this quite successfully for other issues like poor factor or transmission congestion.

 

UK – reducing regulation of competitive activities

 

Introduction

 

A key principle of regulation is that only activities that are not subject to competitive pressures should be regulated ... the UK water regulator OFWAT has recognised this in its framework for the 2015 – 2020 water and sewage price controls. This article uses OFGEM’s proposed lifting of price regulation for Scottish & Southern Energy’s new connection business as a starting point, but then expands into a wider discussion of when regulation should be applied.

 

OFGEM’s proposal

 

OFGEM has been working to facilitate competition in the new network connections market for about 12 years in the belief that competition is more likely to promote innovation, lower prices and customer choice than regulation would. However progress was slow until the 5th price control (EDPCR5) provided for a 4% margin on contestable services, giving new entrant provides something to capture.

 

EDPCR5 also provided for regulated electric companies to seek a lifting of price regulation in markets where they believe effective competition exists. OFGEM seems sufficiently satisfied that effective competition exists in the market for new network connections to propose lifting regulation.

 

Some wider issues

 

Some of the wider issues to be considered include....

 

·       The recognition (including by regulators) that effective competition will generally always result in superior levels of innovation, price-quality trade-offs and customer service than regulation.

 

·       The need for small pieces of ostensibly monopolistic networks that are subject to competition to be excluded from the regulatory regime. That obviously poses some challenges for a regulator, particularly when the wider regulatory regime states something like “all direct control services provided by XYZ Electric Company will be subject to price control” that doesn’t appear to anticipate exempting small pieces of the assets.

 

·       The need for the benefits of regulation to outweigh the costs. If I recall rightly, the New Zealand Gas Inquiry all those years ago concluded that although some gas companies should’ve been subject to price control the cost of doing so would’ve exceeded the benefits to customers. Very refreshing thinking.

 

So ... worth a few moments thought, eh.

 

Australia

 

Aus – the Murraylink Revised Proposal

 

Introduction

 

Readers might remember that about 10 years ago the Murraylink HVDC converted from a market-based service to a regulated network service. This article examines the Murraylink’s Revised Proposal for the 1st July 2013 – 30th June 2023 regulatory period.

 

What exactly is the Murraylink ?

 

Murraylink is a 180km long, 150kV, 220MW HVDC link between Red Cliffs, Victoria and Berri, South Australia. The technology is Insulated Gate Bipolar Transistors (IGBT’s) and perhaps even more uniquely the entire line route is by underground cable.

 

The link was originally built by Hydro Quebec subsidiary TransEnergie Australia but was sold to the APA Group in March 2006.

 

Key aspects of the revised proposal

 

Key parameters of the decision process to date include...

 

Parameter

Original Proposal

Draft Decision

Revised Proposal

Final Decision

Opening RAB

$102.4m

$107.1m

$107.63m

 

Nominal Vanilla WACC

8.61%

7.11%

7.11%

 

CapEx – first 5 years

$13.8m

$7.3m

$6.3m

 

Nominal OpEx – first 5 years

$40.1m

$34.1m

$21.2m

 

 

Pipes & Wires will comment further once the Final Decision is released.

 

North America

 

US – power to the people ?

 

Introduction

 

News emerged recently that New York Governor Andrew Cuomo wants more power over “under-performing utilities”. This article tries to get to the bottom of exactly what Cuomo might be angling for, and presents a few opinions on those matters.

 

What exactly has Cuomo said ?

 

A few of Cuomo’s salient comments include...

 

·       “Progress (at restoration) is occurring, but that progress is unacceptable”.

 

·       “Utility companies have not performed adequately ... they have been told that repeatedly”.

 

·       “They will be held accountable for their lack of performance”. 

 

·       “Yes, it was a catastrophic storm, but they should’ve been prepared, they should’ve been responsive”.

 

What might Cuomo be angling for ?

 

Cuomo is certainly hopping mad, but what might he really be angling for ? The unworthy cynic might well say he is simply tapping a rich vein of voter anger to perpetuate his own political fortunes by targeting the ever-unpopular monopoly businesses, whilst on the other hand at least some customers will probably go along with Cuomo.

 

There is talk of giving state regulators further powers, such as being “able to terminate the relationship” (presumably through the cancellation of a license, which can theoretically occur in many other jurisdictions).

 

What might actually occur ?

 

Well ... it’s a bit hard to know what exactly might occur. But here’s a few thoughts...

 

·       My understanding is that recent regulatory policy in New York has shown a bias towards smart grids, with proposed funding for network hardening being rejected by the NY Public Service Commission. Not surprisingly, smart grids proved to be of little use under salt water.

 

·       Are there other, less draconian, regulatory sanctions (or even perhaps mechanisms that already exist within the regulatory framework) that discourage poor storm response whilst avoiding investment uncertainty.

 

·       What about some carrots to go with the sticks ? Something like allowing extra regulated revenue for increased responsiveness ?

 

·       What might the threat of license termination actually look like ? Would it require a forced sale of assets to the City or State at a non-negotiated price for them to run as a Muni ? My guess is that for starters that would increase investment uncertainty, pushing up the cost of capital which would need to be reflected in higher tariffs.

 

·       Would a competitive business that had the bulk of its means of production fully vulnerable to a catastrophic storm have fared any better (a bit of academic argument, I know, but worth thinking about).

 

·       How much storm protection is enough ? Apparently the bund at the E14th Street substation was 12 feet high, but the incoming water was 14 feet high. I would’ve thought 14 feet of water on the streets of Manhattan would constitute unreasonable circumstances.

 

·       Some careful thought about the urgency for supply restoration is needed. Many customers houses would have presumably still been flooded or at least water damaged, so do we really want to reconnect the electricity early in the play ? 

 

US – more power to the people ?

 

Introduction

 

Relationships between City or State government and investor owned utilities (IOU) can often be tense, often founded on the assumption that a Muni’s tariffs would be lower than an IOU’s tariffs. This article examines an emerging scrap between the City of Boulder, Colorado and Xcel Energy and tries to understand what the issues are and whether the proposed “Muni’ing” of Xcel’s distribution assets might actually work.

 

Note that this is a separate issue from the recent Colorado PUC ruling that Xcel’s Boulder SmartGridCity project hadn’t shown sufficient benefits to justify Xcel recovering the remaining $16.6m of costs. 

 

The current electricity supply arrangement in Boulder

 

The original electricity supply in Boulder was from the Public Service Company of Colorado (PSCo). Through a series of mergers, PSCo became Xcel Energy, which now supplies 3,400,000 electric and 1,900,000 gas customers across Colorado, Michigan, Minnesota, New Mexico, North Dakota, South Dakota, Texas and Wisconsin. Annual revenues are about $10.7b.

 

Boulder began researching alternative supply arrangements in 2005, and commissioned a report which concluded that the City could feasibly purchase Xcel’s distribution assets and keep tariffs comparable to Xcel’s. These plans were shelved in 2008 when Xcel selected Boulder for its SmartGridCity program.

 

The City of Boulder’s concerns

 

The City has a stated suite of energy goals, which include reducing CO2 emissions, providing customers with a greater say about their energy and promoting social justice. It’s not totally clear what the City’s precise concerns are but a quick read of some topical media suggests that the City simply wants more renewable energy. I suspect there is probably also some thinking along the lines that a Muni wouldn’t need to make a profit, hence its tariffs could be lower.

 

The proposed Muni’ing – what might it involve ?

 

After negotiations for the City to partner with Xcel to build a wind farm broke down in July 2011 the City decided to put Muni’ing back on the voter ballot. The City plans to vote on the issue in April, and the expectation is that the vote will be in favor of purchasing Xcel’s distribution business and running it as a Muni.

 

Some issues to think about

 

A few key issues that might need to be considered include....

 

·       The City’s cost estimate to establish and run a Muni is $290m, a long way short of Xcel’s estimate of $1.2b.

 

·       The City plans to supply a lot more renewable energy, and the evidence is that renewables are leading to rapid cost increases. In contrast, Xcel’s generation portfolio includes about 7,700MW of coal-fired stations of which many are large and mature (and should therefore have low costs per MWh).

 

·       A Muni will lack scale, certainly the scale of a company the size of Xcel.

 

·       A Muni will be subject to municipal interference, or perhaps to put it more politely, become an instrument of policy (the City’s energy goals make that abundantly clear).

 

·       Whether the loss of scale (duplication of management and board functions etc) and loss of access to low-cost coal fired generation will off-set any reduction in tariffs from avoiding the IOU model.

 

·       Presumably the City will have to use real $$$ to buy the distribution assets. Somewhere, somehow those funds will have a capital charge. Whether the City makes them explicit on electric accounts or tries to bury them and quietly let Boulderites pay the capital charge through their property taxes remains to be seen.

 

Pipes & Wires will re-examine this in a few months once the City’s vote has occurred.

 

US – recovering the cost of smart grids

 

Introduction

 

Most jurisdictions require some form of regulatory approval to recover costs through regulated tariffs. Investment certainty is improved when this approval is ex-ante, and correspondingly declines when approval can be ex-post ie. the regulatory can disallow recovery after implementation. This article examines the Colorado Public Utility Commission’s (PUC) decision to prevent Xcel Energy subsidiary Public Service Company of Colorado (PSCo) from recovering the final $16.6m of costs of the Boulder SmartGridCity program.

 

What exactly is SmartGridCity ?

 

SmartGridCity is technology pilot program that Xcel Energy is rolling out in the City of Boulder, Colorado. The heart of the program appears to be a roll-out of 23,000 smart meters to determine customer preferences for energy management tools, provide web access to accounts to facilitate energy conservation and demand management, and detect outages.

 

What seems to have gone wrong ?

 

It seems that the following things have gone wrong...

 

·       SmartGridCity was originally costed at $15.3m, but ended up costing something like $45m. It appears that the hardness of the ground in Boulder for installing fiber was significantly under-estimated.

 

·       Real time demand management is not really possible. It appears that some smart kit was not actually installed.

 

·       An apparent under-estimate of just how much demand reduction or energy conservation would actually occur in response to signals such as text messages.

 

What was the PUC’s response ?

 

By March 2012, the PUC had approved recovery of $27.9m, leaving $16.6m outstanding. Recovery of that outstanding $16.6m would require Xcel to inter alia provide strong evidence of customer and community engagement, better defining how customers could make use of smart meters, and better defending its strategic plan.

 

In a decision released in January 2013, the PUC denied Xcel recovery of the balance of the capital costs. At the time of writing, Xcel had not decided whether to appeal the PUC’s decision.

 

House-keeping stuff

 

Opt out from Pipes & Wires

 

Pick this link to opt out from Pipes & Wires. Please ensure that you send from the email address we send Pipes & Wires to.

 

Disclaimer

 

These articles are of a general nature and are not intended as specific legal, consulting or investment advice, and are correct at the time of writing. In particular Pipes & Wires may make forward looking or speculative statements, projections or estimates of such matters as industry structural changes, merger outcomes or regulatory determinations. These articles also summarise lengthy documents, and it is important that readers refer to those documents in forming opinions or taking action.

 

Utility Consultants Ltd accepts no liability for action or inaction based on the contents of Pipes & Wires including any loss, damage or exposure to offensive material from linking to any websites contained herein, or from any republishing by a third-party whether authorised or not, nor from any comments posted on Linked In, Face Book or similar by other parties.